PMP Practice Question: Business Environment — Predictive, Medium

A pharmaceutical company is executing a three-year drug development project using a predictive approach. The project is currently in the clinical trials phase. A competitor unexpectedly announces they will launch a similar drug to market six months earlier than anticipated. The project management office (PMO) director asks the project manager to evaluate strategic options. The current project is on schedule and within budget, but the early competitive launch will significantly reduce the projected market share and return on investment. What is the most appropriate action for the project manager to take?