PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

875 questions found · page 1 of 35

1
Business EnvironmentPredictiveMedium

A project manager is executing a government contract project using a predictive approach. The project has strict compliance requirements and formal change control processes. A new technology solution becomes available that could reduce project costs by 15% and improve the final product's performance. However, implementing this technology would require significant design changes and extend the schedule by two months. The contract includes performance incentives for early completion. What should the project manager evaluate first when considering this opportunity?

November 11, 2026

→
2
Business EnvironmentPredictiveMedium

A project manager is leading a manufacturing facility expansion project. Six months into the 18-month project, the company announces a merger with a competitor. The merger brings uncertainty about future facility requirements, as the combined organization may need different capacity than originally planned. The project baseline called for doubling production capacity, but the merger may change this requirement significantly. Senior leadership has not yet decided whether to continue, pause, or cancel the project. What should the project manager do?

November 11, 2026

→
3
Business EnvironmentPredictiveMedium

A project manager is leading an infrastructure upgrade project for a financial services company. During execution, a major economic downturn occurs, and the organization announces a 20% budget cut across all projects. The CFO has requested all project managers to identify cost reduction options. The project is currently on schedule and within budget, with 30% of the work completed. Several vendors have already been contracted for upcoming phases. What should the project manager prioritize when developing cost reduction recommendations?

November 11, 2026

→
4
Business EnvironmentPredictiveMedium

A pharmaceutical project manager is overseeing a new drug development project using a predictive approach. During the planning phase, the project team identifies that a key competitor has announced a similar product launch scheduled six months before their planned release date. The executive leadership is pressuring the project manager to accelerate the timeline to maintain competitive advantage. However, the project includes mandatory regulatory approval phases that cannot be compressed. What is the best course of action?

November 11, 2026

→
5
Business EnvironmentPredictiveMedium

A project manager is leading a predictive construction project when new environmental regulations are announced that will affect the project's compliance requirements. The project is 40% complete, and the regulations will take effect in three months, midway through the project timeline. The regulatory changes will require additional environmental impact assessments and potentially design modifications. Stakeholders are concerned about project costs and schedule. What should the project manager do first?

November 11, 2026

→
6
ProcessAgileMedium

An agile team working on an e-commerce platform has been using story points for estimation and tracking velocity. After six sprints, a new senior developer joins the team, and velocity increases from an average of 40 points to 55 points per sprint. The product owner is excited about the increased velocity and begins pressuring the team to commit to 55+ points each sprint going forward. However, the team's Definition of Done hasn't changed, and the scope of individual stories remains similar. What should the project manager do to address this situation?

November 11, 2026

→
7
ProcessAgileMedium

Your agile team is developing a financial reporting system for a highly regulated industry. During the sprint, a new compliance regulation is announced that affects functionality planned for the next three sprints. The product owner wants to immediately pivot to address the compliance requirement, which would mean abandoning partially completed work from the current sprint. The team is five days into a two-week sprint and has completed about 60% of their committed work. What should the Scrum Master recommend?

November 11, 2026

→
8
ProcessAgileMedium

A software development team is working on a cloud migration project using Scrum. During the sprint review, stakeholders provide feedback that the user interface doesn't match their expectations, even though it meets all the acceptance criteria defined in the user stories. The product owner approved these acceptance criteria during backlog refinement two weeks ago. Several stakeholders express disappointment and suggest the team wasted the sprint. What is the most appropriate action for the team to take?

November 11, 2026

→
9
ProcessAgileMedium

An agile project team is building a customer portal for an insurance company. During sprint planning, the development team estimates that the highest-priority user story will take 13 story points to complete, but the team's average velocity is only 35 points per two-week sprint and they have already committed to 28 points of other work. The product owner insists this story must be included because a major client has requested this feature for a demo in three weeks. The team is concerned about over-committing. How should the team proceed?

November 11, 2026

→
10
ProcessAgileMedium

Your agile team has completed three sprints of a mobile application development project. During the retrospective, the team identifies that their velocity has been declining from 45 story points in Sprint 1 to 38 in Sprint 2, and 32 in Sprint 3. Team members mention they are spending significant time waiting for answers from the product owner, who is often unavailable due to other commitments. The product owner attends sprint planning and reviews but is rarely available during the sprint. What should the project manager do first to address this situation?

November 11, 2026

→
11
ProcessPredictiveMedium

You are managing a software implementation project for a financial services client using a waterfall methodology. During the design phase, the client's compliance officer requests changes to the security architecture to address new regulatory requirements that were published last month. Implementing these changes will require rework of completed design documents and delay the project by four weeks. The compliance officer emphasizes that non-compliance could result in significant fines. What is the best approach to handle this situation?

November 11, 2026

→
12
ProcessPredictiveMedium

During the planning phase of a pharmaceutical research project, you are developing the project schedule. Several senior researchers insist that certain experimental activities cannot have their durations estimated accurately because the outcomes are uncertain. However, your management wants a detailed schedule with specific milestones for board reporting. The contract includes penalty clauses for late delivery. How should you address duration estimating for these uncertain activities?

November 11, 2026

→
13
ProcessPredictiveMedium

You are managing a manufacturing equipment installation project following a predictive lifecycle. During quality inspections, your quality team identifies that several delivered components do not meet the specifications detailed in the technical requirements document, though they could still function adequately. The supplier claims these components meet industry standards and modifying them would delay delivery by six weeks and increase costs by 15%. The project is currently on schedule and within budget. What should you do?

November 11, 2026

→
14
ProcessPredictiveMedium

Your construction project is halfway through execution when you discover that actual costs are significantly higher than planned. The Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks for your assessment of the situation and whether the project can be completed within the approved budget. You have $2 million remaining in the budget and estimate $3.2 million of work left to complete. What is the most appropriate course of action?

November 11, 2026

→
15
ProcessPredictiveMedium

You are managing a government infrastructure project using a predictive approach. During the executing phase, a key supplier notifies you that they cannot deliver critical materials by the scheduled date due to manufacturing delays, which will impact the critical path by three weeks. The project has a fixed deadline tied to regulatory approval timelines. Your sponsor is concerned about potential penalties. What should you do first?

November 11, 2026

→
16
PeoplePredictiveEasy

You are managing an infrastructure upgrade project using a predictive approach. During the execution phase, one of your high-performing team members requests to attend a three-day industry conference that conflicts with a critical project milestone. The team member believes the conference content would be valuable for their professional development. However, their absence could impact the milestone delivery. What should you do?

November 11, 2026

→
17
PeoplePredictiveEasy

You have just been assigned as project manager for a regulatory compliance project with a fixed deadline in 12 months. The project charter has been approved and you are beginning detailed planning. You need to build your project team, but the functional managers control the resources in your organization. Several functional managers have indicated they can only provide resources with limited availability. What should you do first?

November 11, 2026

→
18
PeoplePredictiveEasy

You are managing a manufacturing project following a predictive life cycle. During project execution, you notice that two team members who must collaborate closely on sequential tasks have very different communication styles. One prefers detailed written documentation while the other prefers quick verbal updates. This difference has started to cause minor delays as they struggle to coordinate effectively. What should you do?

November 11, 2026

→
19
PeoplePredictiveEasy

You are leading a construction project with a detailed work breakdown structure and schedule. One of your experienced team members approaches you privately and expresses concerns that a newer team member is not following the established safety procedures documented in the project management plan. The newer team member has not caused any incidents yet, but the experienced member is worried about potential risks. What is the best course of action?

November 11, 2026

→
20
PeoplePredictiveEasy

You are managing a software development project using a waterfall approach. During the planning phase, you identify that the testing team will need specialized training on new security testing tools before the testing phase begins in six months. The training vendor requires a three-month advance booking. Your team members are currently fully allocated to other projects. What should you do first?

November 11, 2026

→
21
Business EnvironmentAgileHard

Your organization has six agile teams developing different components of an integrated supply chain platform. The platform serves enterprise clients who require 99.9% uptime SLAs. Each team has autonomy over their technology choices and deployment schedules, following agile principles of self-organization. Recently, Team A deployed a service update that inadvertently broke the API contract with Team B's component, causing a 4-hour outage affecting 12 enterprise customers. This is the third integration-related outage in two months. The VP of Engineering wants to implement a centralized architecture review board that must approve all significant technical decisions and deployments. The teams argue this will destroy their agility and velocity. You are asked to recommend an approach that maintains both agility and system reliability. What should you propose?

November 11, 2026

→
22
Business EnvironmentAgileHard

You are managing an agile software development project for a healthcare technology company. During Sprint 7, a major security vulnerability is discovered in a third-party library that your product depends on. The library vendor announces they will not patch the vulnerability and are discontinuing support. Replacing this library requires re-architecting significant portions of the application, estimated at 8-12 sprints of work. Your product is currently deployed at 47 hospital systems serving over 200,000 patients. Regulatory guidance indicates the vulnerability could potentially expose patient health information, but exploitation requires specific technical conditions that your security team believes are unlikely. The product owner wants to continue delivering planned features while gradually replacing the library over the next year. What should you recommend?

November 11, 2026

→
23
Business EnvironmentAgileHard

Your organization operates in a market experiencing rapid technological disruption. Your agile product team has been successfully delivering incremental improvements to the core platform for 18 months. During the latest market analysis, competitive intelligence reveals that two major competitors are launching AI-powered features that could make your product's core value proposition obsolete within 12 months. The executive team is divided: the CEO wants to immediately pivot to AI capabilities, while the COO argues this would abandon your loyal customer base and proven revenue stream. Your product has $4M in annual recurring revenue but growth has plateaued. The team has no AI expertise and the technology would require 6-9 months of experimentation before any market-ready features. What is the most appropriate strategy recommendation?

November 11, 2026

→
24
Business EnvironmentAgileHard

You are leading an agile transformation for a product line within a large manufacturing organization that has traditionally used stage-gate processes. After six months, three agile teams have achieved good velocity and stakeholder satisfaction. However, the finance department insists on maintaining annual budget cycles and requires detailed scope commitments nine months in advance for capital allocation. The CFO states that without predictable cost forecasting, the agile teams cannot receive continued funding. Several product owners are now creating extensive upfront requirements documents to satisfy finance, which is causing teams to revert to waterfall behaviors. How should you address this organizational impediment?

November 11, 2026

→
25
Business EnvironmentAgileHard

Your agile team is developing a digital banking platform in a highly regulated financial services environment. During Sprint 3, a new government regulation is announced that will take effect in 90 days, requiring significant changes to customer authentication processes. The product owner wants to immediately pivot the next three sprints to address compliance, but this would delay several high-value customer features that stakeholders have been expecting. The team's current velocity suggests they cannot deliver both compliance changes and the committed features within the regulatory deadline. What should you do first?

November 11, 2026

→