PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

90 questions found · page 1 of 4

1
ProcessAgileEasy

You are the project manager for an agile marketing campaign development team. During sprint planning, the team has identified 15 user stories they believe they can complete based on their average velocity of 40 story points per sprint. However, two team members will be on vacation for one week during this three-week sprint. The total story points for the 15 stories equal 40. What should the team do?

August 16, 2026

2
ProcessAgileEasy

Your organization is transitioning to agile and you are leading your first Scrum project. At the end of the first sprint, the team has completed 80% of the committed user stories, but none of them fully meet the Definition of Done due to incomplete testing. The product owner is pressuring you to accept the stories as done so they can be demonstrated to stakeholders. What should you do?

August 16, 2026

3
ProcessAgileEasy

You are facilitating a daily standup for your agile development team. One team member mentions they are blocked because they are waiting for access to a testing environment that requires approval from the IT security team. This is the third day this issue has been raised. The team member asks what they should work on while waiting. What should you do as the Scrum Master or agile project leader?

August 16, 2026

4
ProcessAgileEasy

Your agile team is planning their next iteration. During the planning session, team members are estimating user stories using story points. A new developer on the team asks why the team uses story points instead of estimating in hours or days. The team lead explains that story points help with relative sizing. What is the primary benefit of using story points for estimation in agile projects?

August 16, 2026

5
ProcessAgileEasy

You are managing a software development project using Scrum. The team has just completed their second sprint and the product owner wants to see what has been developed. Several features have been coded and unit tested, but integration testing is still pending. The product owner asks when they can review the completed work. What should you do?

August 16, 2026

6
ProcessHybridEasy

A hybrid project has completed three sprints for its software component while the predictive infrastructure component is progressing through its execution phase. The project sponsor asks for a progress report to present to the steering committee. The sponsor wants to understand overall project status in a clear, unified way. What should the project manager provide?

August 13, 2026

7
ProcessHybridEasy

A project manager is overseeing a hybrid project where regulatory compliance work follows a waterfall approach and customer-facing features follow Scrum. During a sprint review, stakeholders request adding a new compliance requirement that affects both components. The compliance work requires detailed documentation and formal approval, while the Scrum team prefers to add items directly to their backlog. What is the best approach to manage this change?

August 13, 2026

8
ProcessHybridEasy

A product owner for a hybrid project needs to create requirements documentation. The project includes both a predictive hardware development phase and an agile software development phase. The hardware specifications must be finalized before manufacturing begins, while the software features will evolve based on user feedback. How should the project manager guide the product owner in documenting requirements?

August 13, 2026

9
ProcessHybridEasy

A project manager is leading a hybrid project where the infrastructure component follows a predictive approach and the software development follows an agile approach. The infrastructure team has just completed their foundation work ahead of schedule, which was a prerequisite for the software team to begin their first iteration. The software team lead asks how they should proceed with planning their upcoming sprint. What should the project manager recommend?

August 13, 2026

10
ProcessHybridEasy

A project team is planning a hybrid project where hardware procurement will follow a predictive approach with fixed contracts, and software configuration will follow Scrum with two-week sprints. The project manager needs to plan how the two components will integrate. The hardware delivery is scheduled for month 3, and software sprints will begin in month 1. What integration approach should the project manager establish?

August 13, 2026

11
Business EnvironmentPredictiveEasy

A project manager is leading a construction project to build a new manufacturing facility. During the planning phase, the sponsor asks how the project aligns with the organization's strategic objectives. The project manager reviews the project charter and identifies that the new facility will increase production capacity by 40%, directly supporting the company's five-year growth plan to expand market share. The sponsor requests a document that formally links the project to these strategic objectives. What document should the project manager provide?

August 11, 2026

12
Business EnvironmentPredictiveEasy

A pharmaceutical company is managing a predictive project to develop a new drug delivery system. Six months into the 18-month project, a competitor announces they will release a similar product in 12 months. The project manager realizes this external change could significantly impact the project's market advantage and business value. The project is currently on schedule and within budget. What should the project manager do first?

August 11, 2026

13
Business EnvironmentPredictiveEasy

A project manager is assigned to lead an infrastructure upgrade project for a government agency. During initial planning, the project manager learns that new regulatory requirements for data security will take effect in three months, midway through the planned project timeline. These regulations will mandate additional security controls that were not included in the original project scope. The project is using a predictive approach with a fixed budget. What is the most appropriate action?

August 11, 2026

14
Business EnvironmentPredictiveEasy

A manufacturing company is implementing an ERP system using a predictive project approach. The project manager notices that the IT department, which will maintain the system after go-live, has not been actively involved in the project. The IT manager mentions they were not aware of specific technical requirements being finalized. The project is 60% complete, and user acceptance testing is scheduled to begin in six weeks. What should the project manager have done differently during project planning?

August 11, 2026

15
Business EnvironmentPredictiveEasy

A project manager is leading a software development project for a retail company using a predictive waterfall methodology. Three months into the project, the company merges with another organization, and the new executive team announces a shift in corporate strategy toward e-commerce rather than brick-and-mortar operations. The current project focuses on in-store point-of-sale systems. The project manager's system is still technically needed but may have reduced priority. What is the best course of action?

August 11, 2026

16
ProcessHybridEasy

You are leading a project that combines agile development sprints with a traditional stage-gate approval process for major releases. The development team has completed all sprint work for the current release, but a quality gate review is scheduled for two weeks from now. The team is asking what they should work on next. What should you recommend?

July 22, 2026

17
ProcessHybridEasy

Your project uses Scrum for software development and a waterfall approach for regulatory compliance activities. During sprint planning, the team identifies they need a compliance review completed before they can implement a new feature. The compliance review is scheduled for next month according to the predictive plan. What is the best way to handle this situation?

July 22, 2026

18
ProcessHybridEasy

You are managing a hybrid project where the development team works in two-week sprints while the infrastructure team follows a predictive approach. The development team has completed their sprint and is ready to deploy, but the infrastructure team needs two more weeks to complete their planned activities. Stakeholders are asking when the feature will be available. What should you do first?

July 22, 2026

19
ProcessHybridEasy

You are managing a project where the design phase follows a predictive approach with detailed upfront planning, but the implementation phase uses Scrum. The design phase has just completed, and you are transitioning to implementation. Several team members who worked on design are asking how they will track progress now. What should you explain to them?

July 22, 2026

20
ProcessHybridEasy

Your hybrid project has a product backlog for agile work and a work breakdown structure (WBS) for predictive components. A new stakeholder requirement emerges that could impact both the agile and predictive portions of the project. The business value is clear, but implementation approach is uncertain. How should you handle adding this requirement?

July 22, 2026

21
ProcessAgileEasy

You are facilitating sprint planning for a web development team. The product owner has prioritized 15 user stories for the upcoming sprint, but based on the team's velocity from the past three sprints (averaging 34 story points), this represents 52 story points of work. Several team members express concern about overcommitment. The product owner insists all stories are important and should be included. How should you proceed?

July 20, 2026

22
ProcessAgileEasy

Your agile team is working on a healthcare application project. A critical regulatory requirement emerges mid-sprint that must be implemented before the product can be released. The team has already committed to several user stories for the current two-week sprint and is on track to complete them. The new requirement will take approximately one week of effort. What is the best approach to handle this situation?

July 20, 2026

23
ProcessAgileEasy

You are the product owner for an e-commerce platform development project. The development team has completed several user stories related to the shopping cart functionality. During the sprint review, you notice that while the features work technically, they don't fully align with the customer experience you envisioned based on recent user feedback. The team is asking you to accept the stories as done. What should you do?

July 20, 2026

24
ProcessAgileEasy

Your agile team has just completed their third sprint of a mobile app development project. During the sprint retrospective, team members express frustration that they keep discovering new technical dependencies mid-sprint, causing them to miss their sprint commitments. The team wants to improve their planning process. What should the team do first to address this issue?

July 20, 2026

25
ProcessAgileEasy

You are managing a software development project using Scrum. During the daily standup, one team member mentions they are blocked because they are waiting for clarification from the product owner on a user story acceptance criterion. The product owner is not present at the standup meeting. Another team member suggests moving forward with their best interpretation of the requirement. What should you do as the Scrum Master?

July 20, 2026