Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
180 questions found · page 1 of 8
A technology company is developing a new software product using a hybrid approach. The architectural design and core platform are planned using predictive methods with defined milestones, while customer-facing features are developed using adaptive sprints with regular releases. A major competitor announces a similar product launch in six months. The executive team asks the project manager how quickly the product can go to market. What should the project manager focus on in their response?
November 18, 2026
A healthcare organization is implementing a new patient records system using a hybrid project approach. The data migration follows a predictive waterfall methodology, while the user interface development uses iterative sprints with physician feedback. During a retrospective, the development team expresses frustration that they cannot get timely decisions from the data migration team, which only meets monthly for phase reviews. This is delaying integration testing. What should the project manager do first?
November 18, 2026
A financial services company is developing a new mobile banking application using a hybrid approach. The infrastructure and database design follow a predictive methodology with detailed upfront planning, while the app features are developed using two-week sprints. The marketing department wants to launch a pilot program in two months, but the infrastructure team reports they need four months to complete their work according to the original plan. What is the best way for the project manager to respond?
November 18, 2026
A retail organization is launching a new e-commerce platform with both fixed and variable requirements. The project uses a hybrid approach where the payment gateway and security features follow a predictive plan, while the user interface and customer experience features are developed iteratively. A new compliance regulation is announced that impacts both the payment security requirements and the user registration process. The regulation must be implemented within three months. How should the project manager address this change?
November 18, 2026
A manufacturing company is implementing a new inventory management system using a hybrid approach. The predictive phases involve hardware installation and network configuration, while the adaptive phases focus on software customization based on user feedback. During sprint planning, the operations manager requests that all hardware installation be completed before any software sprints begin. The project manager needs to decide how to respond to this request. What should the project manager do?
November 18, 2026
You are managing an enterprise software implementation project following a waterfall approach. The project has a core team of eight people, including business analysts, developers, and testers. You've noticed that during team meetings, three team members consistently dominate discussions while the other five rarely contribute ideas or feedback. The quieter team members have valuable expertise that could benefit the project. What should you do to improve team participation?
November 14, 2026
You are managing a manufacturing project with a detailed project schedule and assigned resources. The project sponsor has requested that you prepare a resource management plan. You need to document how you will acquire, develop, and manage the project team throughout the project lifecycle. Which of the following should be included in this plan?
November 14, 2026
You are managing a product development project using a predictive methodology. During a weekly team meeting, one of your team members publicly criticizes another team member's work quality on a recent deliverable, stating it was 'sloppy and unprofessional.' The criticized team member becomes visibly upset and defensive. The tension in the room is affecting the rest of the meeting. How should you respond to this situation?
November 14, 2026
You are leading a construction project following a predictive approach. A new civil engineer has joined your team, replacing someone who left the company. The new engineer has strong technical credentials but has never worked on this type of infrastructure project before. Your project is currently in the execution phase, and the work breakdown structure shows that foundation work will begin in three weeks. What is the most appropriate action to help integrate this team member?
November 14, 2026
You are managing a predictive software development project with a team of 12 developers. During the planning phase, you notice that two senior developers have conflicting ideas about the technical architecture approach. The disagreement is causing delays in finalizing the technical design document, which is needed before coding can begin. The project schedule shows that the design phase should be completed in two weeks. What should you do first?
November 14, 2026
You are managing a hybrid project for a marketing campaign. The creative design work is being managed using Scrum with two-week sprints, while the media buying and placement follows a predictive approach with fixed deadlines. At the end of sprint 2, the creative team has completed designs that need approval before media placement can proceed. The media buying schedule shows placement must begin in one week. What should you do to ensure both components stay coordinated?
November 14, 2026
Your hybrid project includes a hardware component managed predictively and a software component managed using Kanban. The hardware team reports they are on schedule, but the software team's Kanban board shows several items stuck in the 'In Progress' column for over two weeks. The team's work-in-progress (WIP) limit is being exceeded. As the project manager, what should you do?
November 14, 2026
You are leading a hybrid project where regulatory compliance activities follow a predictive approach with formal gate reviews, while user interface development follows an agile approach with two-week sprints. The compliance team has identified a new regulatory requirement that will impact the user interface. The development team is currently in the middle of sprint 3. What is the best way to handle this new requirement?
November 14, 2026
Your organization is implementing a new product using a hybrid approach. The infrastructure setup follows a waterfall methodology, while feature development uses Scrum. You are creating the overall project schedule. The infrastructure team needs four months to complete their work before any development can begin. The product owner wants to see working features as soon as possible. How should you structure the project timeline?
November 14, 2026
You are managing a hybrid project where the design phase follows a predictive approach and the development phase uses iterative sprints. The design team has completed their work and handed off specifications to the development team. However, the development team reports that several requirements are unclear and need clarification. The design team has already moved on to another project. What should you do first?
November 14, 2026
You are managing an infrastructure upgrade project using a predictive approach. During the execution phase, one of your high-performing team members requests to attend a three-day industry conference that conflicts with a critical project milestone. The team member believes the conference content would be valuable for their professional development. However, their absence could impact the milestone delivery. What should you do?
November 11, 2026
You have just been assigned as project manager for a regulatory compliance project with a fixed deadline in 12 months. The project charter has been approved and you are beginning detailed planning. You need to build your project team, but the functional managers control the resources in your organization. Several functional managers have indicated they can only provide resources with limited availability. What should you do first?
November 11, 2026
You are managing a manufacturing project following a predictive life cycle. During project execution, you notice that two team members who must collaborate closely on sequential tasks have very different communication styles. One prefers detailed written documentation while the other prefers quick verbal updates. This difference has started to cause minor delays as they struggle to coordinate effectively. What should you do?
November 11, 2026
You are leading a construction project with a detailed work breakdown structure and schedule. One of your experienced team members approaches you privately and expresses concerns that a newer team member is not following the established safety procedures documented in the project management plan. The newer team member has not caused any incidents yet, but the experienced member is worried about potential risks. What is the best course of action?
November 11, 2026
You are managing a software development project using a waterfall approach. During the planning phase, you identify that the testing team will need specialized training on new security testing tools before the testing phase begins in six months. The training vendor requires a three-month advance booking. Your team members are currently fully allocated to other projects. What should you do first?
November 11, 2026
You have just been assigned as project manager for a new manufacturing project that will use a predictive approach. The project sponsor has approved the project charter, and you are beginning to assemble the project team. Several functional managers have expressed concerns about releasing their best resources for your project. What should you do to secure the resources you need?
November 4, 2026
You are managing a government project using a waterfall approach with a team of 15 people. During the execution phase, you notice that two team members from different departments are having difficulty collaborating on a shared deliverable. They have different working styles and have begun avoiding each other, which is causing delays. What is the best way to address this situation?
November 4, 2026
You are leading a construction project with a detailed project schedule created using the critical path method. A key team member with specialized welding skills will be needed during weeks 8-12 of the project. However, this resource is currently assigned to another project and will not be available until week 10. What should you do first?
November 4, 2026
You are the project manager for a software development project following a waterfall methodology. One of your senior developers has been consistently arriving late to the daily status meetings and missing important updates. This is starting to impact the team's coordination. You have spoken to the developer informally, but the behavior continues. What is the most appropriate next step?
November 4, 2026
You are managing a large infrastructure project using a waterfall approach. During the planning phase, you need to document the roles and responsibilities for all team members and stakeholders. Several team members have overlapping skills, and you want to ensure there is no confusion about who is accountable for each deliverable. What should you create to clearly define these accountabilities?
November 4, 2026
