PMP Practice Question: Process — Agile, Easy

You are the project manager for an agile marketing campaign development team. During sprint planning, the team has identified 15 user stories they believe they can complete based on their average velocity of 40 story points per sprint. However, two team members will be on vacation for one week during this three-week sprint. The total story points for the 15 stories equal 40. What should the team do?