Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
340 questions found · page 1 of 14
A project manager is overseeing a hybrid project to build a new e-commerce platform. The database architecture and payment integration are being developed using a predictive approach due to security requirements and third-party dependencies, while the website features are being delivered through Scrum sprints. The project has a fixed budget of $800,000 and a target completion date in nine months. After four months, earned value analysis shows the predictive components are over budget by 15% with an SPI of 0.85, while the Scrum team is delivering consistently within their sprint budgets. What should the project manager do?
November 23, 2026
A financial services company is running a hybrid project to upgrade its payment processing system. Regulatory compliance and security components are managed predictively with extensive documentation and formal approvals, while the customer-facing features are developed using Kanban. During a compliance audit, auditors request complete traceability of all requirements to test cases and deployment records. The Kanban team has been tracking work items and testing informally through their board and daily standups. What is the best way for the project manager to address the audit requirements?
November 23, 2026
A project manager is leading a hybrid project to develop a new mobile application with backend infrastructure upgrades. The infrastructure work uses a predictive approach with detailed plans and change control, while the application development follows Scrum practices. Three months into the project, the cumulative flow diagram shows that work items in the 'testing' state have been increasing steadily, while the 'done' column shows minimal progress. The predictive infrastructure tasks are on schedule. What should the project manager do to address this situation?
November 23, 2026
A manufacturing company is executing a hybrid project to modernize its production line. The hardware installation follows a predictive waterfall approach due to vendor constraints and safety regulations, while software configuration is managed through two-week sprints. During the fourth sprint review, stakeholders request significant changes to the reporting dashboard that would require three additional sprints to implement. However, the hardware installation is scheduled to complete in five weeks, and production must begin immediately afterward. How should the project manager address this situation?
November 23, 2026
A project manager is leading a hybrid project to implement a new customer relationship management (CRM) system. The infrastructure and data migration components are being delivered using a predictive approach with fixed milestones, while the user interface customization is being developed iteratively using Scrum. During sprint planning, the development team identifies dependencies on the data migration work, which is running two weeks behind schedule. The team is concerned they won't be able to complete their committed sprint work without the migrated data. What should the project manager do first?
November 23, 2026
You are managing a government infrastructure project using a hybrid approach. The construction follows a predictive critical path method, while the smart building automation system uses incremental delivery with four-week iterations. You are currently in the execution phase. The construction team has encountered unexpected soil conditions requiring foundation redesign, delaying their schedule by three months. The automation system team has completed two iterations successfully and is ready to begin the third iteration, which requires installing sensors in the foundation area. The finance department is questioning why you are continuing to spend money on the automation system when the construction delay means those components cannot be installed on schedule. What is the MOST appropriate response?
November 23, 2026
Your hybrid project has been running for six months with a core platform being built predictively (now 60% complete) and customer-facing features being developed in two-week sprints by multiple Scrum teams. The product owner has identified a new market opportunity that requires pivoting the feature priorities significantly. However, implementing these new priorities would require changes to the platform architecture that the predictive team is currently building. The platform team is reluctant to make changes, citing the impact on their schedule and budget baseline. The product owner argues that agility means being able to respond to change. What should you do?
November 23, 2026
You are leading a pharmaceutical product development project using a hybrid approach: clinical trials follow strict FDA-regulated predictive processes, while the patient monitoring mobile app is developed using Kanban. During a regulatory audit, the auditor questions why there is no comprehensive integrated project schedule with all dependencies mapped. The auditor expresses concern that the lack of a traditional Gantt chart for the mobile app work indicates poor project control. Your clinical trials schedule is detailed and compliant. The mobile app team has a well-maintained Kanban board with cycle time metrics showing consistent delivery. How should you respond?
November 23, 2026
Your organization is implementing a new customer portal using a hybrid approach. The infrastructure team is following a predictive waterfall approach with stage gates, while three application development teams use two-week Scrum sprints. You are in month 4 of the 12-month project. The infrastructure team has just informed you they need to push their Stage 2 completion from month 6 to month 8 due to vendor delays in delivering cloud infrastructure components. The application teams are progressing well and will be ready to begin integration testing in month 6 as planned. Senior management is concerned about the schedule impact. What is the BEST way to adjust your approach?
November 23, 2026
You are managing a hybrid project where the hardware component follows a predictive lifecycle and the software component uses Scrum. The hardware team has completed their design phase and is ready to begin procurement, which has a 16-week lead time. However, the software team has just discovered during Sprint Review that a critical integration requirement was misunderstood, requiring significant hardware specification changes. The hardware procurement contracts are ready for signature. Stakeholders are pressuring you to proceed with procurement to avoid schedule delays. What should you do first?
November 23, 2026
You are managing a hybrid project for a marketing campaign. The creative design work is being managed using Scrum with two-week sprints, while the media buying and placement follows a predictive approach with fixed deadlines. At the end of sprint 2, the creative team has completed designs that need approval before media placement can proceed. The media buying schedule shows placement must begin in one week. What should you do to ensure both components stay coordinated?
November 14, 2026
Your hybrid project includes a hardware component managed predictively and a software component managed using Kanban. The hardware team reports they are on schedule, but the software team's Kanban board shows several items stuck in the 'In Progress' column for over two weeks. The team's work-in-progress (WIP) limit is being exceeded. As the project manager, what should you do?
November 14, 2026
You are leading a hybrid project where regulatory compliance activities follow a predictive approach with formal gate reviews, while user interface development follows an agile approach with two-week sprints. The compliance team has identified a new regulatory requirement that will impact the user interface. The development team is currently in the middle of sprint 3. What is the best way to handle this new requirement?
November 14, 2026
Your organization is implementing a new product using a hybrid approach. The infrastructure setup follows a waterfall methodology, while feature development uses Scrum. You are creating the overall project schedule. The infrastructure team needs four months to complete their work before any development can begin. The product owner wants to see working features as soon as possible. How should you structure the project timeline?
November 14, 2026
You are managing a hybrid project where the design phase follows a predictive approach and the development phase uses iterative sprints. The design team has completed their work and handed off specifications to the development team. However, the development team reports that several requirements are unclear and need clarification. The design team has already moved on to another project. What should you do first?
November 14, 2026
An agile team working on an e-commerce platform has been using story points for estimation and tracking velocity. After six sprints, a new senior developer joins the team, and velocity increases from an average of 40 points to 55 points per sprint. The product owner is excited about the increased velocity and begins pressuring the team to commit to 55+ points each sprint going forward. However, the team's Definition of Done hasn't changed, and the scope of individual stories remains similar. What should the project manager do to address this situation?
November 11, 2026
Your agile team is developing a financial reporting system for a highly regulated industry. During the sprint, a new compliance regulation is announced that affects functionality planned for the next three sprints. The product owner wants to immediately pivot to address the compliance requirement, which would mean abandoning partially completed work from the current sprint. The team is five days into a two-week sprint and has completed about 60% of their committed work. What should the Scrum Master recommend?
November 11, 2026
A software development team is working on a cloud migration project using Scrum. During the sprint review, stakeholders provide feedback that the user interface doesn't match their expectations, even though it meets all the acceptance criteria defined in the user stories. The product owner approved these acceptance criteria during backlog refinement two weeks ago. Several stakeholders express disappointment and suggest the team wasted the sprint. What is the most appropriate action for the team to take?
November 11, 2026
An agile project team is building a customer portal for an insurance company. During sprint planning, the development team estimates that the highest-priority user story will take 13 story points to complete, but the team's average velocity is only 35 points per two-week sprint and they have already committed to 28 points of other work. The product owner insists this story must be included because a major client has requested this feature for a demo in three weeks. The team is concerned about over-committing. How should the team proceed?
November 11, 2026
Your agile team has completed three sprints of a mobile application development project. During the retrospective, the team identifies that their velocity has been declining from 45 story points in Sprint 1 to 38 in Sprint 2, and 32 in Sprint 3. Team members mention they are spending significant time waiting for answers from the product owner, who is often unavailable due to other commitments. The product owner attends sprint planning and reviews but is rarely available during the sprint. What should the project manager do first to address this situation?
November 11, 2026
You are managing a software implementation project for a financial services client using a waterfall methodology. During the design phase, the client's compliance officer requests changes to the security architecture to address new regulatory requirements that were published last month. Implementing these changes will require rework of completed design documents and delay the project by four weeks. The compliance officer emphasizes that non-compliance could result in significant fines. What is the best approach to handle this situation?
November 11, 2026
During the planning phase of a pharmaceutical research project, you are developing the project schedule. Several senior researchers insist that certain experimental activities cannot have their durations estimated accurately because the outcomes are uncertain. However, your management wants a detailed schedule with specific milestones for board reporting. The contract includes penalty clauses for late delivery. How should you address duration estimating for these uncertain activities?
November 11, 2026
You are managing a manufacturing equipment installation project following a predictive lifecycle. During quality inspections, your quality team identifies that several delivered components do not meet the specifications detailed in the technical requirements document, though they could still function adequately. The supplier claims these components meet industry standards and modifying them would delay delivery by six weeks and increase costs by 15%. The project is currently on schedule and within budget. What should you do?
November 11, 2026
Your construction project is halfway through execution when you discover that actual costs are significantly higher than planned. The Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks for your assessment of the situation and whether the project can be completed within the approved budget. You have $2 million remaining in the budget and estimate $3.2 million of work left to complete. What is the most appropriate course of action?
November 11, 2026
You are managing a government infrastructure project using a predictive approach. During the executing phase, a key supplier notifies you that they cannot deliver critical materials by the scheduled date due to manufacturing delays, which will impact the critical path by three weeks. The project has a fixed deadline tied to regulatory approval timelines. Your sponsor is concerned about potential penalties. What should you do first?
November 11, 2026
