PMP Practice Question: ProcessAgile, Hard

Your agile team is building a healthcare platform that must comply with HIPAA regulations. The compliance officer insists on reviewing and approving all designs before development begins and all code before deployment, which creates a bottleneck taking 5-7 days per review. The team's sprint cycle is two weeks, and this delay means most stories cannot be completed within a sprint. The compliance officer is unwilling to attend daily standups or sprint ceremonies, stating they are too busy. Team morale is declining as they cannot meet sprint goals. What is the MOST effective approach to resolve this situation?