PMP Practice Question: Process — Predictive, Medium
You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
Study this topic
- 📖Cost Estimation Techniques: From ROM to Definitive Estimates
Master the cost estimation methods tested on the PMP exam, from rough order of magnitude to definitive estimates, with practical examples and calculation techniques.
- 📖Financial Management for Project Managers: A 2026 PMP Guide
Master the financial management skills tested in the 2026 PMP exam. Learn budget forecasting, value delivery, and financial decision-making aligned with the expanded Business Environment domain.
- 🗂️Flashcards: Earned Value Management (EVM) Formulas
16 cards · quick recall practice
More Process Questions
View all →You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
Your agile team has been working on a mobile banking application for three sprints. During the current sprint review, the product owner expresses dissatisfaction because the authentication feature doesn't match their vision, even though it meets all acceptance criteria that were discussed during sprint planning. The team completed all committed stories and the feature is technically sound. Several stakeholders at the review agree with the product owner's concerns. The product owner wants to reject the story and have it reworked immediately. What should you do first?
