Your organization is executing a hybrid project to implement a new financial system. The software configuration follows an adaptive approach with two-week iterations, while data migration and cutover activities are planned predictively due to strict regulatory windows. You're currently in iteration 5 of 10. During a governance review, the CFO requests a detailed status report showing percentage complete for the entire project and exact completion dates for all remaining work. Your adaptive team tracks progress using velocity and burndown charts. How should you respond to this request?