PMP Practice Question: Process — Agile, Medium
A cross-functional agile team is developing a customer portal. After four sprints, the cumulative flow diagram shows that items are moving from 'In Development' to 'In Testing' quickly, but there is a growing bottleneck in the testing column, with an average of 12 items waiting for test completion while only 3-4 items are in development at any time. The testers report they are working at full capacity. What should the team do?
Study this topic
- 📖WBS Work Breakdown Structure: Proven Best Practices
Master the essential techniques for creating effective Work Breakdown Structures that drive project success and align with modern delivery approaches.
- 📖Schedule Management Techniques for Modern Project Teams
Master critical path, critical chain, agile scheduling, and hybrid approaches for the 2026 PMP exam. Learn practical techniques that align with PMBOK 8th Edition principles.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
