PMP Guide — Empowering Project Managers
ProcessAgileMediumECO: Process Task 4.2

PMP Practice Question: Process — Agile, Medium

Your Scrum team has a definition of done that includes code review, unit testing, and deployment to the staging environment. During sprint planning, the team realizes that one of the high-priority user stories will require changes to the production database schema, which according to organizational policy requires a change control board (CCB) approval that typically takes 5-7 business days. The sprint is only 10 business days long. What is the best approach?

← All questions

Study this topic