PMP Practice Question: ProcessHybrid, Medium

You are managing a hybrid project implementing a new customer relationship management (CRM) system. The infrastructure and data migration components follow a predictive approach with fixed deliverables, while the user interface customization uses iterative sprints. During the third sprint review, stakeholders request significant changes to the reporting dashboard that would require substantial rework to the data warehouse already built in the predictive phase. The data warehouse is 80% complete and on schedule. What should you do first?