PMP Practice Question: Process — Hybrid, Medium

Your organization is implementing a new financial system using a hybrid approach. Core system configuration follows a predictive waterfall methodology, while user interface customization uses Scrum. You are in month four of an eight-month project. The predictive stream reports on schedule with 50% completion, but the Scrum team's velocity has been declining for three sprints, and they've completed only 35% of anticipated story points. The product owner is frustrated with the pace. What should you do?