PMP Guide — Empowering Project Managers
Process · 16 cards

Earned Value Management (EVM) Formulas

Every earned value formula you need for the PMP exam — variances, performance indexes, forecasts (EAC, ETC, VAC) and TCPI — with how to interpret each result.

Card 1 of 160 / 16 marked as known

All 16 cards in this deck

  1. 1.What is Planned Value (PV)?Show answer

    The authorized budget assigned to the work scheduled to be completed by a given point in time.

  2. 2.What is Earned Value (EV)?Show answer

    The budgeted value of the work actually completed by a given point in time.

  3. 3.What is Actual Cost (AC)?Show answer

    The actual cost incurred for the work performed by a given point in time.

  4. 4.What is Budget at Completion (BAC)?Show answer

    The total budget for all the work on the project — the sum of all planned values.

  5. 5.Formula for Cost Variance (CV)Show answer

    CV = EV − AC. Negative means over budget; positive means under budget.

  6. 6.Formula for Schedule Variance (SV)Show answer

    SV = EV − PV. Negative means behind schedule; positive means ahead of schedule.

  7. 7.Formula for Cost Performance Index (CPI)Show answer

    CPI = EV ÷ AC. Below 1.0 means over budget (getting less than $1 of value per $1 spent); above 1.0 means under budget.

  8. 8.Formula for Schedule Performance Index (SPI)Show answer

    SPI = EV ÷ PV. Below 1.0 means behind schedule; above 1.0 means ahead of schedule.

  9. 9.EAC formula when current cost performance is expected to continue (typical variance)Show answer

    EAC = BAC ÷ CPI

  10. 10.EAC formula when the past variance is a one-off and future work will go as planned (atypical variance)Show answer

    EAC = AC + (BAC − EV)

  11. 11.EAC formula when both cost and schedule performance will affect the remaining workShow answer

    EAC = AC + [(BAC − EV) ÷ (CPI × SPI)]

  12. 12.EAC formula when the original estimate is no longer validShow answer

    EAC = AC + bottom-up ETC (a fresh estimate of the remaining work).

  13. 13.Formula for Estimate to Complete (ETC)Show answer

    ETC = EAC − AC. The expected cost to finish the remaining work.

  14. 14.Formula for Variance at Completion (VAC)Show answer

    VAC = BAC − EAC. Negative means the project is forecast to finish over budget.

  15. 15.Formula for To-Complete Performance Index (TCPI) to finish on the original budgetShow answer

    TCPI = (BAC − EV) ÷ (BAC − AC). Above 1.0 means the remaining work must be done more efficiently than planned.

  16. 16.Formula for TCPI to finish on a revised estimate (EAC)Show answer

    TCPI = (BAC − EV) ÷ (EAC − AC)

Get daily PMP practice questions

Free scenario-based questions aligned with the 2026 ECO, delivered to your inbox.

No spam. Unsubscribe anytime. Protected by reCAPTCHA (Privacy · Terms).

More flashcard decks

Ready to apply it? Try scenario-based practice questions or the printable PMP cheat sheet.