Earned Value Management (EVM) Formulas
Every earned value formula you need for the PMP exam — variances, performance indexes, forecasts (EAC, ETC, VAC) and TCPI — with how to interpret each result.
All 16 cards in this deck
1.What is Planned Value (PV)?Show answer
The authorized budget assigned to the work scheduled to be completed by a given point in time.
2.What is Earned Value (EV)?Show answer
The budgeted value of the work actually completed by a given point in time.
3.What is Actual Cost (AC)?Show answer
The actual cost incurred for the work performed by a given point in time.
4.What is Budget at Completion (BAC)?Show answer
The total budget for all the work on the project — the sum of all planned values.
5.Formula for Cost Variance (CV)Show answer
CV = EV − AC. Negative means over budget; positive means under budget.
6.Formula for Schedule Variance (SV)Show answer
SV = EV − PV. Negative means behind schedule; positive means ahead of schedule.
7.Formula for Cost Performance Index (CPI)Show answer
CPI = EV ÷ AC. Below 1.0 means over budget (getting less than $1 of value per $1 spent); above 1.0 means under budget.
8.Formula for Schedule Performance Index (SPI)Show answer
SPI = EV ÷ PV. Below 1.0 means behind schedule; above 1.0 means ahead of schedule.
9.EAC formula when current cost performance is expected to continue (typical variance)Show answer
EAC = BAC ÷ CPI
10.EAC formula when the past variance is a one-off and future work will go as planned (atypical variance)Show answer
EAC = AC + (BAC − EV)
11.EAC formula when both cost and schedule performance will affect the remaining workShow answer
EAC = AC + [(BAC − EV) ÷ (CPI × SPI)]
12.EAC formula when the original estimate is no longer validShow answer
EAC = AC + bottom-up ETC (a fresh estimate of the remaining work).
13.Formula for Estimate to Complete (ETC)Show answer
ETC = EAC − AC. The expected cost to finish the remaining work.
14.Formula for Variance at Completion (VAC)Show answer
VAC = BAC − EAC. Negative means the project is forecast to finish over budget.
15.Formula for To-Complete Performance Index (TCPI) to finish on the original budgetShow answer
TCPI = (BAC − EV) ÷ (BAC − AC). Above 1.0 means the remaining work must be done more efficiently than planned.
16.Formula for TCPI to finish on a revised estimate (EAC)Show answer
TCPI = (BAC − EV) ÷ (EAC − AC)
More flashcard decks
Ready to apply it? Try scenario-based practice questions or the printable PMP cheat sheet.
