PMP Practice Question: ProcessAgile, Hard

An agile team working on a cloud migration project has been using story points for estimation with planning poker. After 10 sprints, a new senior developer joins who strongly advocates for switching to ideal hours instead of story points, arguing that hours are more precise and easier for stakeholders to understand. The team is divided—some members agree with the new developer, while others want to keep story points because their historical velocity data would become irrelevant. The upcoming sprint planning is in two days, and the product owner is concerned about any changes that might impact the team's predictability during a critical release cycle. What should you do?