PMP Practice Question: Process — Agile, Hard
Your agile team has been working on a financial services application for three sprints. During the sprint review, the product owner asks the team to demonstrate a complex regulatory reporting feature that was not part of the sprint backlog. The team lead explains they focused on the agreed sprint goal instead. The product owner becomes frustrated, stating this feature is critical for an upcoming audit and should have been obvious to include. Stakeholders at the meeting appear concerned about the team's ability to deliver. What should the Scrum Master do to address this situation?
Study this topic
- 📖Emotional Intelligence for the PMP Exam 2026: Master the People Domain
Emotional intelligence accounts for crucial skills tested across the People domain (33%) in the 2026 PMP exam. Learn how EI appears in scenarios, key competencies, and proven study strategies.
- 📖Breaking Into Project Management: PMP Certification for Career Changers
Career changers face unique challenges pursuing PMP certification. Learn how to meet eligibility requirements, build project experience, and position yourself for a successful transition.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?