PMP Guide — Empowering Project Managers
ProcessAgileEasyECO: Process Task 3.2

PMP Practice Question: ProcessAgile, Easy

Your organization is transitioning to agile and you are leading your first Scrum project. At the end of the first sprint, the team has completed 80% of the committed user stories, but none of them fully meet the Definition of Done due to incomplete testing. The product owner is pressuring you to accept the stories as done so they can be demonstrated to stakeholders. What should you do?