PMP Practice Question: Process — Hybrid, Medium

Your hybrid project uses waterfall for regulatory compliance activities and Scrum for product feature development. During sprint planning, the development team identifies dependencies on compliance documentation that won't be ready for another three weeks according to the predictive schedule. The product owner wants to prioritize high-value features that require this documentation. Several team members suggest working on lower-priority features first. What is the best approach?