PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

250 questions found · page 1 of 10

1
PeopleHybridHard

You are managing a high-stakes hybrid project with a fixed regulatory deadline. The core development uses Scrum, while compliance documentation follows a stage-gate process. Two months from the deadline, your most experienced developer, James, who understands both the technical and regulatory requirements, gives two weeks' notice. He is irreplaceable in the timeline remaining. The team is already at maximum capacity. James mentions he's leaving because he feels the organization doesn't value his contributions despite his critical role. What is your most important immediate action?

October 9, 2026

→
2
PeopleHybridHard

Your organization is transitioning to hybrid delivery. You are managing a pilot project with both predictive and agile components. The project steering committee, composed of executives unfamiliar with agile, insists on detailed monthly status reports showing percent complete for all work packages, including the agile sprints. Your agile team lead argues this contradicts agile principles and will force the team to waste time on meaningless estimates. The steering committee controls project funding and has expressed concern about the "lack of visibility" into agile work. How should you address this situation?

October 9, 2026

→
3
PeopleHybridHard

You are leading a transformation program using a hybrid approach. Three months in, you notice that Maria, a senior business analyst on the predictive track, consistently delivers exceptional requirements documentation but frequently criticizes the agile team's "incomplete" user stories in cross-functional meetings. The agile product owner has stopped inviting Maria to refinement sessions, creating a silo. Maria has 20 years of experience and is technically correct that user stories lack the detail of traditional requirements. However, her approach is damaging collaboration. What should you do?

October 9, 2026

→
4
PeopleHybridHard

Your hybrid project has a distributed team across four time zones. The predictive workstream team meets face-to-face weekly and has strong cohesion. The agile workstream operates virtually with daily standups but team members rarely interact beyond ceremonies. Velocity has plateaued, and retrospectives reveal team members feel disconnected. The agile coach suggests mandatory video-on policies and virtual team-building activities. Several senior developers privately tell you they find these activities juvenile and prefer focusing on work. What is the best approach to improve team cohesion?

October 9, 2026

→
5
PeopleHybridHard

You are managing a hybrid project where the infrastructure team uses waterfall and the application development team uses Scrum. During sprint planning, the development team commits to features requiring network configuration changes. The infrastructure team, working from a fixed schedule defined six months ago, informs you they cannot accommodate the changes until next quarter. The development team is frustrated and threatens to escalate to executives. Stakeholders expect the features in three weeks. What should you do first?

October 9, 2026

→
6
PeoplePredictiveMedium

You are managing a telecommunications infrastructure project using a predictive approach. The project team includes specialists from engineering, procurement, and installation departments. During project planning, you identified that the engineering team needs to complete detailed designs before procurement can begin vendor selection, and installation cannot start until equipment arrives. You've created a detailed schedule with these dependencies. However, the engineering manager informs you that his team is being pulled to support an emergency on another project and will be unavailable for three weeks, which will impact your critical path. What is the best way to handle this situation?

October 5, 2026

→
7
PeoplePredictiveMedium

You are managing a manufacturing project following a predictive life cycle. During a milestone review, you discover that one of your team leads has consistently overstated the completion percentage of their work packages in status reports. Upon investigation, you find the actual progress is about 20% behind what was reported, though the work quality is acceptable. This team lead has been with the company for 15 years and is generally reliable. The project is now showing as on-track when it is actually behind schedule. What should be your first course of action?

October 5, 2026

→
8
PeoplePredictiveMedium

You are leading a construction project with a detailed work breakdown structure and baseline schedule. A team member who is relatively new to the organization approaches you privately and mentions that they feel intimidated by the project's senior architect, who frequently dismisses their input during technical meetings. The team member is responsible for quality inspections and their observations are important for project success. The senior architect is known for being direct but has excellent technical expertise. How should you address this situation?

October 5, 2026

→
9
PeoplePredictiveMedium

You are managing a software development project using a waterfall methodology. During the development phase, your lead developer informs you that she has received a job offer from another company and will be leaving in three weeks. She is the only team member with deep knowledge of the legacy system integration, which is critical for the next phase. The project is currently on schedule, and this phase is expected to complete in two months. What is the most effective action to take?

October 5, 2026

→
10
PeoplePredictiveMedium

You are managing a large infrastructure project using a predictive approach with a team of 45 members across three locations. During the executing phase, you notice that two senior engineers from different locations are in constant disagreement about technical specifications, causing delays in deliverables. The project schedule shows this work is on the critical path. Both engineers are highly skilled and have worked on similar projects before. What should you do first to address this situation?

October 5, 2026

→
11
PeopleHybridMedium

You are managing a product development project using a hybrid approach. The UX design work follows a phase-gate process to ensure brand consistency, while development uses Scrum. During Sprint 5, a major competitor launches a similar product with a feature your team planned for Sprint 8. The product owner wants to reprioritize immediately and skip the UX design review to accelerate delivery. The UX lead insists that bypassing the design process will create technical debt and brand inconsistency. Both are escalating to you. What is your best course of action?

October 4, 2026

→
12
PeopleHybridMedium

Your organization is piloting a hybrid approach on a strategic initiative. The predictive-focused PMO requires detailed monthly status reports with earned value metrics, while your agile team tracks progress through burndown charts and sprint reviews. Team members are spending six hours per month translating their agile metrics into PMO templates, and they're frustrated by what they perceive as duplicative reporting. The PMO director insists on standardized reporting for portfolio visibility. How should you address this situation?

October 4, 2026

→
13
PeopleHybridMedium

You are leading a hybrid project where regulatory compliance work follows a waterfall approach due to audit requirements, while new feature development uses Kanban. A senior developer who excels at iterative development has been assigned to document compliance procedures, a predictive task requiring detailed upfront planning. The developer is frustrated, producing low-quality documentation, and has privately expressed feeling underutilized. Meanwhile, a compliance specialist is struggling with the ambiguity of Kanban flow. What should you do?

October 4, 2026

→
14
PeopleHybridMedium

Your hybrid project team includes five co-located developers working in two-week sprints and three distributed subject matter experts who contribute according to a predictive schedule with monthly milestones. The SMEs have missed two consecutive touchpoints, causing the development team to make assumptions that later required rework. The SMEs claim they were unaware of the specific timing of developer needs. You need to improve team cohesion and reduce waste. What is the most effective approach?

October 4, 2026

→
15
PeopleHybridMedium

You are managing a hybrid project where the development team uses Scrum for product features while the infrastructure team follows a waterfall approach. During sprint planning, the development team commits to delivering a new customer portal feature. However, the infrastructure team later reports they cannot provision the required cloud servers until their phase-gate approval is completed in three weeks, which will cause the sprint goal to fail. Team morale is declining as developers feel blocked. What should you do first?

October 4, 2026

→
16
PeoplePredictiveHard

You are managing a predictive construction project to build a new hospital wing with a 36-month timeline and $45M budget. Your team of 40 members includes architects, engineers, contractors, and hospital operational staff. At the 18-month mark, during earned value analysis, you identify that CPI is 0.92 and SPI is 0.88. In reviewing team performance data, you notice that the top 20% of your team members are producing 60% of the project value, while several team members are consistently underperforming against their assigned tasks. The human resource management plan includes a performance measurement approach, but you have not conducted formal performance reviews due to project pressures. Several stakeholders have commented on specific individuals not meeting expectations. Union agreements require 90-day notice for any personnel changes. What should you prioritize?

September 29, 2026

→
17
PeoplePredictiveHard

You are managing a predictive pharmaceutical project developing a new drug delivery system with a fixed 18-month regulatory submission deadline. Your team includes research scientists, regulatory specialists, and manufacturing engineers. Six months into the project, you notice that the scientists are creating highly detailed technical documentation that far exceeds regulatory requirements, while the regulatory team complains this slows down their review process. The scientists argue that thorough documentation is part of their professional standards. Meanwhile, manufacturing engineers are waiting for finalized specifications to begin their work, and this path is now on the critical path with only two weeks of float remaining. The quality management plan specifies documentation standards that the scientists are exceeding. How should you address this situation?

September 29, 2026

→
18
PeoplePredictiveHard

You are managing a multi-year predictive ERP implementation project for a global manufacturing company. The project organizational chart shows a matrixed structure where team members report both to you and their functional managers. Three months into execution, you discover that five critical team members are consistently being pulled back to operations by their functional managers to address production issues, causing them to miss 40% of their planned project hours. This has resulted in two successive missed milestones. You have raised this issue in the last two steering committee meetings, but functional managers argue that production takes priority. The project charter clearly states resource commitment levels, and the sponsor supported the project publicly but has not intervened. What should be your next step?

September 29, 2026

→
19
PeoplePredictiveHard

You are leading a predictive aerospace project with strict quality gates and regulatory requirements. Your project team of 25 members has been working together for nine months. During a critical design review, you notice that two senior engineers from different functional departments consistently undermine each other's technical approaches in meetings, creating tension that is now affecting team morale. Other team members have started taking sides, and collaboration has noticeably decreased. The project sponsor mentions that both engineers are highly regarded in the organization and have worked together on previous projects without issues. You have a major milestone deliverable due in four weeks that requires their joint contribution. What is the most effective approach?

September 29, 2026

→
20
PeoplePredictiveHard

You are managing a large government infrastructure project using a predictive approach with a 24-month timeline. During month 8, your technical lead submits his resignation, citing personal reasons. This individual has deep knowledge of legacy systems that interface with your new solution, and no documentation exists for these integrations. The resource manager offers you two options: promote a junior team member who has been shadowing the technical lead for three months, or bring in an external consultant with general expertise but no project-specific knowledge. Your project is currently on schedule, but the next phase involves critical integration work starting in six weeks. What should you do first?

September 29, 2026

→
21
PeopleAgileMedium

You are coaching a newly formed agile team that includes three junior developers and two senior developers. During the first two sprints, you notice the senior developers are completing most of the complex stories while junior developers are assigned only simple tasks. The senior developers say they are trying to help the team meet commitments, but the junior developers express frustration in private that they are not learning new skills. Sprint goals are being met, but you are concerned about long-term team capability and sustainability. What is the best approach?

September 29, 2026

→
22
PeopleAgileMedium

Your agile team has two developers who consistently clash during daily standups and sprint planning. One developer prefers thoroughly discussing technical approaches before committing to work, while the other prefers to start coding quickly and iterate. Their disagreements are starting to affect team dynamics, with other team members avoiding engaging in technical discussions. Both developers are highly skilled and their work quality is excellent. Yesterday, their disagreement during refinement caused the session to run 30 minutes over time. What should you do?

September 29, 2026

→
23
PeopleAgileMedium

During a sprint review, a key stakeholder becomes visibly upset when seeing the increment, stating that the features demonstrated are not what they expected, even though the stories were approved during sprint planning. The product owner defends the work, saying the team delivered exactly what was written in the user stories. The stakeholder insists the team must redo the work. Team morale drops immediately as they feel their hard work is being dismissed. How should you address this conflict?

September 29, 2026

→
24
PeopleAgileMedium

Your agile development team includes members from four different countries across three time zones. During sprint planning, you notice that team members in the Asia-Pacific region rarely speak up, while team members in North America dominate the conversation. The sprint retrospectives show similar patterns. The team's velocity has been declining over the past two sprints, and some stories are being carried over because requirements were misunderstood. What is the most effective action to improve team collaboration?

September 29, 2026

→
25
PeopleAgileMedium

You are leading an agile project team that has been working together for three sprints. During the latest retrospective, several team members express frustration that decisions are often delayed because they feel they need to wait for your approval on minor implementation details. The team has strong technical skills and has consistently met their sprint commitments. Team velocity is stable, but you notice team members seem hesitant to self-organize. What should you do to address this situation?

September 29, 2026

→