PeopleHybridMediumECO: People Task 1.1

You are leading a hybrid project where the development team works in two-week sprints while the infrastructure team follows a waterfall approach with phase gates. During sprint planning, a senior developer publicly criticizes a junior team member's previous work, causing visible discomfort. The junior member becomes withdrawn for the remainder of the meeting. Several team members later approach you expressing concern about the negative team dynamics. What should you do first to address this situation?