PMP Practice Question: People — Predictive, Medium

You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?

← All questions

Study this topic

More People Questions

View all →
1
MediumPredictive

You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?

→
2
MediumPredictive

You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?

→
3
MediumPredictive

You are managing a predictive software development project with a team of 12 members. During the executing phase, you notice that two senior developers frequently disagree during technical design meetings, causing delays in decision-making. The disagreements are becoming personal, and other team members are starting to take sides. The project schedule shows that critical design decisions must be finalized within two weeks to avoid impacting downstream activities. What should you do FIRST to address this situation?

→