PeopleHybridMediumECO: People Task 2.4

Your hybrid project has a distributed team across three time zones. The agile software development team conducts daily standups, while the regulatory compliance team works in traditional phases with monthly reviews. You notice that collaboration between these groups is minimal, causing delays when compliance requirements impact sprint deliverables. The compliance lead insists their work cannot be broken into smaller increments, while the development team lead complains about last-minute compliance changes. What is the best approach to improve collaboration?