Your agile development team is struggling to complete stories within sprints. During planning, developers frequently say they cannot estimate stories because requirements are unclear. The product owner insists the stories are sufficiently detailed and becomes defensive when the team asks questions. This pattern has repeated for four sprints, causing incomplete work and team frustration. As the project manager, what is your best course of action?