PMP Practice Question: People — Hybrid, Easy
You are managing a hybrid project where part of the team works in two-week sprints while another group follows a traditional waterfall approach for regulatory compliance activities. During a recent sprint review, the agile team demonstrated completed features, but several waterfall team members expressed confusion about what was delivered and how it impacts their documentation work. Team morale appears to be declining due to this disconnect. What should you do first to address this situation?
Study this topic
- 📖Psychological Safety in Project Teams: A PMP Essential
Psychological safety drives team performance and innovation. Learn how to create trust, encourage risk-taking, and build high-performing project teams aligned with PMBOK 8 principles.
- 📖Best AI Tools for Project Managers: Tested & Reviewed
Discover which AI tools actually help project managers work smarter in 2026. We tested leading platforms for scheduling, risk analysis, stakeholder communication, and decision support.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More People Questions
View all →You are managing a construction project using a predictive approach. The project is in the execution phase, and you have a baseline schedule with clearly defined milestones. One of your key team members, who is responsible for electrical installations, requests three weeks of leave for personal reasons during a critical phase of the project. This team member has specialized expertise that is difficult to replace. The leave would occur just before a major milestone delivery. What is the BEST course of action?
You are leading a manufacturing facility construction project following a predictive lifecycle. The project team consists of 15 members, including contractors and internal staff. After three months of work, you receive feedback from several team members that the weekly status meetings are too long and not productive. Team members feel they spend too much time listening to updates irrelevant to their work. The meetings currently last 90 minutes and cover all work packages. What is the best approach to address this concern?
You are leading a manufacturing implementation project using a predictive lifecycle. The project team consists of members from three different departments who have not worked together before. After one month of execution, you observe that team members primarily communicate within their departmental groups, and cross-functional collaboration is minimal. Work hand-offs between departments are experiencing delays and quality issues. The project charter emphasizes the importance of integrated teamwork for project success. What should you do to improve this situation?