Your predictive manufacturing project is entering the execution phase with a baseline schedule approved by all stakeholders. You discover that a key subject matter expert, who was promised to your project at 50% allocation, is now only available 20% due to competing organizational priorities. This resource was critical for your planned knowledge transfer sessions with the implementation team. The functional manager apologizes but says they cannot change the allocation. What should you do?