PMP Practice Question: ProcessAgile, Medium

Your agile team has completed three sprints of a mobile application project. During the sprint retrospective, team members report that they consistently cannot complete all planned story points because unexpected production support issues from a legacy system consume 30-40% of their capacity each sprint. The product owner is frustrated with the reduced velocity and wants the team to commit to more story points. What should the scrum master do first?