PMP Practice Question: Process — Agile, Medium
Your agile team has completed three sprints of a mobile application project. During the sprint retrospective, team members report that they consistently cannot complete all planned story points because unexpected production support issues from a legacy system consume 30-40% of their capacity each sprint. The product owner is frustrated with the reduced velocity and wants the team to commit to more story points. What should the scrum master do first?
Study this topic
- 📖Emotional Intelligence for the PMP Exam 2026: Master the People Domain
Emotional intelligence accounts for crucial skills tested across the People domain (33%) in the 2026 PMP exam. Learn how EI appears in scenarios, key competencies, and proven study strategies.
- 📖Servant Leadership in Agile Project Management (2026 PMP)
Master servant leadership for the 2026 PMP exam. Learn how this critical agile approach drives team performance, aligns with PMBOK 8, and supports the People domain.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
