PMP Practice Question: ProcessAgile, Hard

An agile team is delivering a customer-facing mobile application using two-week sprints. After six sprints, velocity has been stable at 40 story points per sprint, but customer satisfaction scores are declining. Analysis shows that while features are being delivered on schedule, they often require significant rework in subsequent sprints after user feedback. The product owner has been accepting all stories that meet the acceptance criteria at sprint reviews. Technical debt is accumulating, and the team's Definition of Done includes unit testing and code review but no user validation. What is the BEST approach to improve customer satisfaction?