PMP Practice Question: ProcessHybrid, Medium

Your hybrid project is developing a medical device with hardware components managed predictively due to manufacturing lead times and regulatory submissions, while the embedded software uses iterative development with monthly releases. You have just completed the third software iteration when the hardware team discovers a component obsolescence issue that will delay hardware delivery by two months. The software team has three more iterations of features planned that depend on the specific hardware configuration. What should you do?