PMP Practice Question: Process — Agile, Medium
An agile project team has been using story points and velocity for sprint planning. After six sprints, a new team member joins who is much more experienced than the rest of the team and significantly increases productivity. The team's velocity jumps from an average of 32 points per sprint to 48 points. The product owner sees this increase and immediately adds more items to the upcoming sprint based on the new velocity. However, two weeks later, the experienced team member accepts a position at another company. What should the team have done differently?
Study this topic
- 📖Agile Sprint Planning Techniques for the 2026 PMP Exam
Master sprint planning techniques essential for the 2026 PMP exam. Learn how to apply timeboxing, capacity planning, and story estimation in hybrid environments.
- 📖Earned Value Management: Complete PMP Exam Study Guide
Master EVM formulas, interpretation, and application for the PMP exam. Learn how earned value management integrates with agile, hybrid, and predictive approaches in the 2026 ECO.
- 🗂️Flashcards: Schedule, Estimating & Financial Formulas
14 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
