An agile project team has been using story points and velocity for sprint planning. After six sprints, a new team member joins who is much more experienced than the rest of the team and significantly increases productivity. The team's velocity jumps from an average of 32 points per sprint to 48 points. The product owner sees this increase and immediately adds more items to the upcoming sprint based on the new velocity. However, two weeks later, the experienced team member accepts a position at another company. What should the team have done differently?