PMP Guide — Empowering Project Managers
ProcessHybridMediumECO: Process Task 3.3

PMP Practice Question: Process — Hybrid, Medium

Your organization is implementing a hybrid project to modernize its payment processing system. The core payment engine follows a waterfall approach with strict regulatory requirements and formal testing gates, while the mobile app interface is developed using Scrum with two-week sprints. You are currently planning the integration testing phase. The payment engine team requests a four-week notice before any integration point, while the Scrum team wants to integrate continuously as features are completed. How should you handle this conflict in integration approaches?

← All questions

Study this topic