PMP Practice Question: Business Environment — Predictive, Easy
A manufacturing company is implementing an ERP system using a predictive project approach. The project manager notices that the IT department, which will maintain the system after go-live, has not been actively involved in the project. The IT manager mentions they were not aware of specific technical requirements being finalized. The project is 60% complete, and user acceptance testing is scheduled to begin in six weeks. What should the project manager have done differently during project planning?
Study this topic
- 📖Breaking Into Project Management: PMP Certification for Career Changers
Career changers face unique challenges pursuing PMP certification. Learn how to meet eligibility requirements, build project experience, and position yourself for a successful transition.
- 📖AI and Automation: What the PMP Exam Tests in 2026
The 2026 PMP exam introduces AI and automation as testable topics. Learn what you need to know about AI tools, ethical considerations, and integration strategies.
- 🗂️Flashcards: Leadership, Team & Stakeholder Models
15 cards · quick recall practice
More Business Environment Questions
View all →A project manager is leading a hybrid project to implement a new customer relationship management (CRM) system. The predictive phase involves infrastructure setup and data migration, while the adaptive phase covers user interface customization based on feedback. During planning, the sponsor asks how benefits will be measured throughout the project lifecycle. What should the project manager do to align with organizational benefit realization?
A project manager is working on a hybrid project to modernize a legacy billing system. The organization has a strong compliance department that requires detailed documentation for audit purposes. The adaptive team members express concern that creating comprehensive documentation conflicts with agile principles. What should the project manager do to balance these competing demands?
A project manager is leading a hybrid project to launch a new e-commerce platform. The infrastructure deployment follows a predictive approach, while feature development uses Scrum. During a retrospective, the Scrum team reports frustration that infrastructure dependencies are blocking their work. The infrastructure team says they are following their plan and cannot accommodate unplanned requests. What should the project manager do?