PMP Practice Question: Business Environment — Hybrid, Easy

A project manager is leading a hybrid project to implement a new customer relationship management (CRM) system. The predictive phase involves infrastructure setup and data migration, while the adaptive phase covers user interface customization based on feedback. During planning, the sponsor asks how benefits will be measured throughout the project lifecycle. What should the project manager do to align with organizational benefit realization?