You are managing a hybrid project where the development team works in two-week sprints while the infrastructure team follows a predictive approach. The development team has completed their sprint and is ready to deploy, but the infrastructure team needs two more weeks to complete their planned activities. Stakeholders are asking when the feature will be available. What should you do first?