Your agile team is working on a healthcare application project. A critical regulatory requirement emerges mid-sprint that must be implemented before the product can be released. The team has already committed to several user stories for the current two-week sprint and is on track to complete them. The new requirement will take approximately one week of effort. What is the best approach to handle this situation?