Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
485 questions found · page 2 of 20
You are managing a defense contractor project with 30 team members working on classified deliverables. Three months into the project, a key architect who designed the overall solution structure has received a more lucrative offer from a competitor and will leave in two weeks. This architect's knowledge is essential for the next phase, and direct replacement is complicated by security clearance requirements that take 4-6 months. You have identified an internal candidate with relevant experience but who lacks the specific domain expertise. The project baseline includes detailed technical specifications, but much of the architect's design rationale exists only in email threads and meeting notes. Your sponsor is pressing you to maintain the current schedule. What is your best course of action?
August 20, 2026
You are managing a large construction project that has entered the execution phase. During a routine performance review, you discover that one of your site supervisors has been consistently inflating progress reports for the past three weeks, showing 85% completion when actual completion is closer to 65%. This supervisor is well-liked by the team, has 15 years of experience, and this is the first time you've encountered integrity issues with this individual. The misinformation has affected your earned value calculations and led you to reassign resources that were actually still needed. The project is visible to executive leadership, and you have a steering committee meeting in two days. What is the most appropriate course of action?
August 20, 2026
You are leading a pharmaceutical project to develop validation documentation for a new manufacturing process. The project team includes quality assurance specialists, process engineers, and regulatory affairs experts. During a critical review meeting, you observe that the QA specialists consistently dismiss input from the process engineers, citing regulatory concerns, while the engineers feel the QA team doesn't understand operational realities. This dynamic has resulted in rework cycles and is threatening the project's ability to meet regulatory submission deadlines. The organizational matrix structure gives you limited authority over these functional resources. How should you address this situation?
August 20, 2026
You are managing a government contract project following a predictive approach with strict scope, schedule, and budget constraints. During month 4 of the 12-month project, a key team member who holds critical institutional knowledge about legacy systems unexpectedly resigns. This team member was responsible for integrating the new system with three legacy platforms, and replacement hiring could take 6-8 weeks due to security clearance requirements. The integration work is scheduled to begin in 3 weeks. Your team suggests aggressively cross-training other members, but this would require pulling resources from their current critical path activities. What should you prioritize first?
August 20, 2026
You are managing a complex infrastructure project with a team of 45 members across three geographical locations. During the executing phase, you notice that two senior technical leads from different locations are consistently disagreeing on technical approaches during virtual meetings, causing delays in decision-making. The disagreements have begun to affect team morale, and other team members are starting to take sides. Both leads are highly skilled and their expertise is critical to project success. The project is currently on schedule but at risk of delays if this conflict continues. What is the most appropriate action to take?
August 20, 2026
You are leading a pharmaceutical project using a hybrid model where clinical trial protocols follow FDA-mandated predictive processes, while patient recruitment and engagement strategies use adaptive methods with two-week iterations. During a retrospective, the adaptive team identifies that current recruitment messaging isn't resonating with target demographics and wants to pivot their approach. However, any changes to patient-facing materials require review under the predictive compliance process, which takes four weeks. The trial needs to meet enrollment targets within three months. What is the most appropriate action?
August 20, 2026
Your organization is implementing a new financial system using a hybrid approach. Core system configuration follows a predictive waterfall methodology, while user interface customization uses Scrum. You are in month four of an eight-month project. The predictive stream reports on schedule with 50% completion, but the Scrum team's velocity has been declining for three sprints, and they've completed only 35% of anticipated story points. The product owner is frustrated with the pace. What should you do?
August 20, 2026
You are managing a construction project using a hybrid approach where procurement and permitting follow predictive methods, while interior design decisions use an adaptive approach with frequent client feedback loops. The permits have been delayed by two weeks, which will impact the construction schedule. The client is eager to continue making design decisions in their regular review sessions. Your project budget has limited contingency remaining. How should you proceed?
August 20, 2026
Your hybrid project uses waterfall for regulatory compliance activities and Scrum for product feature development. During sprint planning, the development team identifies dependencies on compliance documentation that won't be ready for another three weeks according to the predictive schedule. The product owner wants to prioritize high-value features that require this documentation. Several team members suggest working on lower-priority features first. What is the best approach?
August 20, 2026
You are managing a hybrid project where the design phase follows a predictive approach while development uses Scrum sprints. The design team has completed 70% of their work according to the project schedule, but stakeholders are now requesting significant design changes based on early market feedback. The development team is ready to start their first sprint but needs finalized designs. The project sponsor is concerned about timeline impacts. What should you do first?
August 20, 2026
You are managing a hybrid project where the marketing deliverables follow a predictive schedule tied to a product launch date, while the product features are developed iteratively. A high-performing developer has been consistently helping marketing team members learn new tools and solve technical problems, but this is impacting their ability to complete sprint commitments. The marketing manager wants this support to continue, saying it's invaluable. The Scrum Master is concerned about sprint goal achievement. How should you handle this situation?
August 17, 2026
Your hybrid project has a core team co-located in the office and three remote team members in different time zones who joined recently. The co-located team members have strong working relationships and often make decisions during informal hallway conversations. The remote members have expressed frustration about being excluded from decisions and learning about changes after they've been made. Sprint retrospectives show declining satisfaction scores from remote team members. What should you do to address this?
August 17, 2026
You are leading a product development project using a hybrid approach where requirements are managed predictively but delivery occurs in two-week iterations. A key stakeholder who funded the project has been unavailable for the past month and missed the last two sprint reviews. The team has questions about priorities and acceptance criteria, causing them to make assumptions. Another stakeholder with less authority has been attending and providing direction that contradicts the original requirements. What is your best course of action?
August 17, 2026
Your hybrid project team includes five experienced waterfall practitioners and three agile coaches. During retrospectives, the waterfall practitioners rarely speak up, and later you discover they feel their perspectives aren't valued in agile ceremonies. One veteran team member privately tells you they feel the agile approach dismisses the importance of upfront planning. Team velocity has plateaued for three iterations. How should you address this situation?
August 17, 2026
You are managing a hybrid project where the development team uses Scrum for software delivery while the infrastructure team follows a predictive approach. During sprint planning, the development team commits to features that require infrastructure changes, but the infrastructure team says they need two weeks advance notice to schedule their work. This misalignment has caused delays in the past two sprints. What should you do first to address this situation?
August 17, 2026
You are the project manager for an agile marketing campaign development team. During sprint planning, the team has identified 15 user stories they believe they can complete based on their average velocity of 40 story points per sprint. However, two team members will be on vacation for one week during this three-week sprint. The total story points for the 15 stories equal 40. What should the team do?
August 16, 2026
Your organization is transitioning to agile and you are leading your first Scrum project. At the end of the first sprint, the team has completed 80% of the committed user stories, but none of them fully meet the Definition of Done due to incomplete testing. The product owner is pressuring you to accept the stories as done so they can be demonstrated to stakeholders. What should you do?
August 16, 2026
You are facilitating a daily standup for your agile development team. One team member mentions they are blocked because they are waiting for access to a testing environment that requires approval from the IT security team. This is the third day this issue has been raised. The team member asks what they should work on while waiting. What should you do as the Scrum Master or agile project leader?
August 16, 2026
Your agile team is planning their next iteration. During the planning session, team members are estimating user stories using story points. A new developer on the team asks why the team uses story points instead of estimating in hours or days. The team lead explains that story points help with relative sizing. What is the primary benefit of using story points for estimation in agile projects?
August 16, 2026
You are managing a software development project using Scrum. The team has just completed their second sprint and the product owner wants to see what has been developed. Several features have been coded and unit tested, but integration testing is still pending. The product owner asks when they can review the completed work. What should you do?
August 16, 2026
You are managing a hybrid project to implement an enterprise resource planning (ERP) system. The system configuration follows a predictive approach with detailed requirements and formal testing phases, while the change management and user adoption activities use an adaptive approach with iterative training sessions and feedback loops. Your project is currently in the user acceptance testing (UAT) phase for the predictive stream. Users participating in UAT are providing feedback that should inform the next iteration of training materials in the adaptive stream, but the training team says they have already locked their next iteration plan and starting new work would disrupt their sprint commitment. How should you proceed?
August 16, 2026
Your hybrid project is developing a medical device with hardware components managed predictively due to manufacturing lead times and regulatory submissions, while the embedded software uses iterative development with monthly releases. You have just completed the third software iteration when the hardware team discovers a component obsolescence issue that will delay hardware delivery by two months. The software team has three more iterations of features planned that depend on the specific hardware configuration. What should you do?
August 16, 2026
You are leading a hybrid software development project where infrastructure deployment follows a predictive methodology with formal change control, while application features are developed using Kanban. During a retrospective, the development team expresses frustration that infrastructure changes take 3-4 weeks to implement through the change advisory board (CAB), creating bottlenecks for feature delivery. The infrastructure team is concerned that bypassing the CAB process could create security and stability risks. Several features are now blocked waiting for infrastructure changes. What is the best approach to address this issue?
August 16, 2026
Your organization is implementing a hybrid project to modernize its payment processing system. The core payment engine follows a waterfall approach with strict regulatory requirements and formal testing gates, while the mobile app interface is developed using Scrum with two-week sprints. You are currently planning the integration testing phase. The payment engine team requests a four-week notice before any integration point, while the Scrum team wants to integrate continuously as features are completed. How should you handle this conflict in integration approaches?
August 16, 2026
You are managing a hybrid project implementing a new customer relationship management (CRM) system. The infrastructure and data migration components follow a predictive approach with fixed deliverables, while the user interface customization uses iterative sprints. During the third sprint review, stakeholders request significant changes to the reporting dashboard that would require substantial rework to the data warehouse already built in the predictive phase. The data warehouse is 80% complete and on schedule. What should you do first?
August 16, 2026
