PMP Practice Question: Process — Agile, Hard
You are leading an agile transformation for a financial services organization. After four months, three of your five scrum teams have adapted well, but two teams continue to struggle with completing their sprint commitments. Analysis shows these teams have significant dependencies on a legacy system team that works in two-week cycles but doesn't use agile practices. The legacy team cannot attend daily standups or sprint ceremonies due to their own schedule. This dependency causes delays in 60% of the struggling teams' stories. Senior management is pressuring you to show improved velocity metrics. What is the most effective approach to address this systemic impediment?
Study this topic
- 📖Coaching and Mentoring in Agile Teams: A PMP Perspective
Learn how servant leadership, coaching, and mentoring drive agile team performance. Essential knowledge for PMP candidates preparing for the 2026 exam's expanded agile focus.
- 📖Critical Path Method: Mastering CPM for Project Success
Learn how to master the Critical Path Method for the PMP exam and real-world project management. Understand float calculation, network diagrams, and schedule optimization techniques.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
