PMP Practice Question: Process — Predictive, Easy
You are managing a product development project using a predictive approach. The project management plan has been approved and execution has begun. During a team meeting, you realize that several team members are unclear about their specific responsibilities and who has decision-making authority for various project activities. This confusion is beginning to cause delays. What document should you reference or update to clarify these roles and responsibilities?
Study this topic
- 📖Resource Management Techniques: Building High-Performing Teams
Master resource management techniques for the PMP exam—from team development to capacity planning. Learn how to optimize human, material, and financial resources for project success.
- 📖Cost Estimation Techniques: From ROM to Definitive Estimates
Master the cost estimation methods tested on the PMP exam, from rough order of magnitude to definitive estimates, with practical examples and calculation techniques.
- 🗂️Flashcards: Risk Responses, Reserves & Contract Types
14 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?