ProcessHybridHardECO: Process Task 1.5

Your organization is executing a hybrid project to implement an enterprise system. The data migration and infrastructure components use a predictive approach with detailed WBS and Gantt charts, while business process customization follows Scrum. During the fourth sprint, the team discovers that the assumed data structure from the migration plan is incompatible with a critical business process they're configuring. Resolving this requires changes to both the migration approach and already-completed sprint work. The infrastructure team resists changes to their plan, citing baseline control processes. What is the best way to proceed?