A cross-functional agile team is building a data analytics platform. During Sprint 6, a critical production bug is discovered in functionality delivered two sprints ago that is affecting customer reporting. Fixing the bug will require approximately 13 story points of effort. The current sprint backlog contains 32 story points of planned work, matching the team's average velocity. The Product Owner wants to add the bug fix to the current sprint without removing any planned stories. What should the Scrum Master recommend?