PMP Practice Question: Process — Agile, Medium
A cross-functional agile team is building a data analytics platform. During Sprint 6, a critical production bug is discovered in functionality delivered two sprints ago that is affecting customer reporting. Fixing the bug will require approximately 13 story points of effort. The current sprint backlog contains 32 story points of planned work, matching the team's average velocity. The Product Owner wants to add the bug fix to the current sprint without removing any planned stories. What should the Scrum Master recommend?
Study this topic
- 📖Issue and Risk Logs: Complete Guide for Project Managers
Master issue and risk log management with proven techniques aligned with PMBOK 8th Edition. Learn how to track, prioritize, and resolve project challenges effectively.
- 📖Critical Path Method: Mastering CPM for Project Success
Learn how to master the Critical Path Method for the PMP exam and real-world project management. Understand float calculation, network diagrams, and schedule optimization techniques.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
