PMP Practice Question: Process — Agile, Medium
A software development team is working on an e-commerce platform using two-week sprints. During sprint planning for Sprint 5, the Product Owner presents 15 user stories totaling 55 story points. Based on their velocity from the last three sprints (average: 34 story points), the team knows they cannot complete all stories. The Product Owner insists all stories are critical for an upcoming trade show demo in four weeks. The team is concerned about committing to work they cannot complete. What is the best approach for the team to take?
Study this topic
- 📖Agile Sprint Planning Techniques for the 2026 PMP Exam
Master sprint planning techniques essential for the 2026 PMP exam. Learn how to apply timeboxing, capacity planning, and story estimation in hybrid environments.
- 📖Governance Frameworks and PMO for the 2026 PMP Exam
Master governance frameworks and PMO structures for the 2026 PMP exam. Learn how organizational governance connects to the expanded Business Environment domain.
- 🗂️Flashcards: Agile, Scrum & Hybrid Concepts
15 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
