An agile team working on a financial services application has maintained a consistent velocity of 28-32 story points over the past six sprints. During Sprint 7 planning, the team estimates several user stories and realizes they are consistently giving higher estimates than in previous sprints for similar work. When asked, team members mention they are concerned about upcoming regulatory requirements that might require rework, though the specific requirements won't be finalized until next quarter. The Product Owner is concerned that velocity is decreasing. What should the team do to address this situation?