PMP Practice Question: Process — Agile, Medium
An agile team working on a financial services application has maintained a consistent velocity of 28-32 story points over the past six sprints. During Sprint 7 planning, the team estimates several user stories and realizes they are consistently giving higher estimates than in previous sprints for similar work. When asked, team members mention they are concerned about upcoming regulatory requirements that might require rework, though the specific requirements won't be finalized until next quarter. The Product Owner is concerned that velocity is decreasing. What should the team do to address this situation?
Study this topic
- 📖Navigating Regulatory Compliance in Project Management
Master regulatory compliance strategies for the PMP exam. Learn how to navigate legal requirements, industry standards, and governance frameworks across project lifecycles.
- 📖Risk Management PMP Exam: Complete Strategic Guide
Master risk management for the PMP exam with strategic insights on identification, assessment, and response planning aligned with PMBOK 8 principles.
- 🗂️Flashcards: Schedule, Estimating & Financial Formulas
14 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?
