PMP Guide — Empowering Project Managers

Practice Questions

PMP Practice Questions

Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.

140 questions found · page 1 of 6

1
PeoplePredictiveMedium

You are managing a predictive product development project for a manufacturing company. The project team includes subject matter experts from engineering, quality, and production departments. During the design phase, you notice that the quality manager, who is a key stakeholder, rarely attends scheduled project meetings and has not responded to several requests for review and approval of critical deliverables. This is causing delays in the approval process. When you finally reach him by phone, he mentions he's very busy with operational issues. What is the most effective action?

August 20, 2026

2
PeoplePredictiveMedium

Your predictive construction project has a baseline schedule of 18 months with defined milestones. You have a team of 40 people including contractors and full-time employees. The project sponsor has just informed you that due to budget constraints, three of your planned team members will not be available for the next phase starting in two months. These positions were critical to the resource management plan. The sponsor asks you to proceed with the reduced team and maintain the original schedule. What should you do first?

August 20, 2026

3
PeoplePredictiveMedium

You are leading a predictive software development project with a defined project plan and detailed WBS. Three months into execution, one of your key developers informs you privately that she is overwhelmed with her assigned tasks and feels she doesn't have the necessary skills to complete a critical module due next month. She is embarrassed and asks you not to tell other team members. The module is on the critical path, and her performance reviews from her functional manager have always been excellent. What is the best approach to help this team member?

August 20, 2026

4
PeoplePredictiveMedium

You are managing a large infrastructure project with a team of 25 members following a predictive approach. During the execution phase, you notice that two senior engineers are having recurring disagreements about technical implementation details, which is causing delays in deliverables. The disagreements occur during team meetings and are beginning to affect team morale. Other team members have started choosing sides, and productivity has decreased by 15% over the past two weeks. What should you do first to address this situation?

August 20, 2026

5
PeoplePredictiveMedium

You are managing a predictive IT infrastructure upgrade project with a diverse team including members from three different countries and time zones. The project is four months into a 12-month schedule. You've noticed during virtual status meetings that team members from the Asia-Pacific region rarely speak up or challenge ideas, even when you know from private conversations that they have valuable concerns and alternative suggestions. Team members from North America tend to dominate discussions. This dynamic is preventing the team from making the best decisions. What should you do to improve team collaboration?

August 20, 2026

6
PeoplePredictiveHard

You are managing a defense contractor project with 30 team members working on classified deliverables. Three months into the project, a key architect who designed the overall solution structure has received a more lucrative offer from a competitor and will leave in two weeks. This architect's knowledge is essential for the next phase, and direct replacement is complicated by security clearance requirements that take 4-6 months. You have identified an internal candidate with relevant experience but who lacks the specific domain expertise. The project baseline includes detailed technical specifications, but much of the architect's design rationale exists only in email threads and meeting notes. Your sponsor is pressing you to maintain the current schedule. What is your best course of action?

August 20, 2026

7
PeoplePredictiveHard

You are managing a large construction project that has entered the execution phase. During a routine performance review, you discover that one of your site supervisors has been consistently inflating progress reports for the past three weeks, showing 85% completion when actual completion is closer to 65%. This supervisor is well-liked by the team, has 15 years of experience, and this is the first time you've encountered integrity issues with this individual. The misinformation has affected your earned value calculations and led you to reassign resources that were actually still needed. The project is visible to executive leadership, and you have a steering committee meeting in two days. What is the most appropriate course of action?

August 20, 2026

8
PeoplePredictiveHard

You are leading a pharmaceutical project to develop validation documentation for a new manufacturing process. The project team includes quality assurance specialists, process engineers, and regulatory affairs experts. During a critical review meeting, you observe that the QA specialists consistently dismiss input from the process engineers, citing regulatory concerns, while the engineers feel the QA team doesn't understand operational realities. This dynamic has resulted in rework cycles and is threatening the project's ability to meet regulatory submission deadlines. The organizational matrix structure gives you limited authority over these functional resources. How should you address this situation?

August 20, 2026

9
PeoplePredictiveHard

You are managing a government contract project following a predictive approach with strict scope, schedule, and budget constraints. During month 4 of the 12-month project, a key team member who holds critical institutional knowledge about legacy systems unexpectedly resigns. This team member was responsible for integrating the new system with three legacy platforms, and replacement hiring could take 6-8 weeks due to security clearance requirements. The integration work is scheduled to begin in 3 weeks. Your team suggests aggressively cross-training other members, but this would require pulling resources from their current critical path activities. What should you prioritize first?

August 20, 2026

10
PeoplePredictiveHard

You are managing a complex infrastructure project with a team of 45 members across three geographical locations. During the executing phase, you notice that two senior technical leads from different locations are consistently disagreeing on technical approaches during virtual meetings, causing delays in decision-making. The disagreements have begun to affect team morale, and other team members are starting to take sides. Both leads are highly skilled and their expertise is critical to project success. The project is currently on schedule but at risk of delays if this conflict continues. What is the most appropriate action to take?

August 20, 2026

11
Business EnvironmentPredictiveHard

A global technology company is executing a predictive project to standardize enterprise resource planning (ERP) systems across 47 subsidiaries in 23 countries, with a 42-month timeline and $310M budget. During month 28, while implementing in the European region, the company's board approves a significant corporate restructuring that will consolidate the 47 subsidiaries into 12 global business units organized by product line rather than geography. This restructuring will change reporting structures, business processes, financial consolidation requirements, and potentially the entire ERP architecture. The project has successfully implemented the system in 18 subsidiaries, with 12 more in various implementation stages. The CIO asks the project manager to assess the impact and recommend how to proceed. What should the project manager do first?

August 16, 2026

12
Business EnvironmentPredictiveHard

A manufacturing company is executing a predictive project to build a $220M production facility for automotive components in an emerging market. The project is month 21 of a 36-month timeline, with building construction complete and equipment installation beginning. Economic conditions in the target market have deteriorated significantly—currency devaluation of 35%, increased import tariffs on raw materials, and two major automotive customers have delayed their regional expansion plans by 2-3 years. The original business case projected ROI of 18% over 8 years based on specific production volumes and pricing. The CFO has requested an updated financial analysis and is considering project termination or conversion to a smaller-scale facility. Equipment purchases worth $78M are committed but not yet delivered. What should the project manager do?

August 16, 2026

13
Business EnvironmentPredictiveHard

A financial services company is executing a core banking system replacement project using a predictive methodology with a 30-month timeline and $95M budget. The project has completed detailed requirements, design, and procurement phases. During the development phase (month 16), the company acquires a smaller competitor that uses a different technology platform. The merger integration team proposes consolidating onto a single platform, which would either require abandoning the current project (wasting $42M invested) or forcing the acquired bank to migrate twice—first to their interim platform, then to the new system within 18 months. The PMO director asks the project manager to evaluate strategic options. Regulatory requirements mandate system consolidation within 24 months of acquisition closing. What analysis should the project manager prioritize?

August 16, 2026

14
Business EnvironmentPredictiveHard

A government infrastructure project worth $420M is in its execution phase using a predictive approach with a 5-year timeline. The project is building a regional transportation hub with multiple contractors. Three years into execution, a new administration takes office with different policy priorities and appoints a new agency director who questions the project's strategic alignment. The director requests a comprehensive benefits realization review before authorizing the next $150M funding tranche. Current earned value metrics show: SPI = 0.92, CPI = 0.88, with 58% of work completed. The project business case was approved under different economic assumptions, and inflation has increased costs by 14%. How should the project manager approach this situation?

August 16, 2026

15
Business EnvironmentPredictiveHard

A multinational pharmaceutical company is executing a predictive drug development project with a 4-year timeline and $180M budget. During year 2, a competitor receives FDA fast-track designation for a similar drug, potentially reducing the market window by 18 months. The project sponsor pressures the project manager to compress the schedule by overlapping clinical trial phases, which would violate regulatory protocols and risk patient safety. The governance board is split—some members prioritize speed-to-market while others emphasize compliance. Financial analysts project a $250M revenue loss if the competitor launches first. What should the project manager do first?

August 16, 2026

16
Business EnvironmentPredictiveMedium

A project manager is leading a predictive product development project in a highly regulated medical device industry. Six months into the twelve-month project, a major competitor fails a regulatory audit, causing the regulatory agency to increase scrutiny across the entire industry. The agency announces more frequent inspections and stricter documentation requirements. The project's quality management plan was based on previous regulatory standards. The project is currently on schedule and within budget. What is the most appropriate action?

August 11, 2026

17
Business EnvironmentPredictiveMedium

A project manager is executing a predictive ERP implementation project for a manufacturing company. During a steering committee meeting, the CFO announces that the company is acquiring a smaller competitor, which will add 200 employees and two manufacturing facilities within four months. The acquisition was not anticipated in the project planning. The current project scope covers only the existing organization structure. Several stakeholders immediately suggest expanding the project scope to include the acquired company. What should the project manager do next?

August 11, 2026

18
Business EnvironmentPredictiveMedium

A pharmaceutical project manager is leading a predictive approach drug development project. The organization's strategic focus has shifted toward personalized medicine, while the current project focuses on a traditional mass-market drug. The project is 40% complete and on track to meet all success criteria. During a portfolio review meeting, executives question whether resources should be reallocated to projects better aligned with the new strategy. The project has strong clinical trial results and a clear path to regulatory approval. What should the project manager do?

August 11, 2026

19
Business EnvironmentPredictiveMedium

A construction project manager is overseeing a three-year infrastructure project using a predictive approach. After the first year, a competitor announces a new building technology that could reduce costs by 15% and improve energy efficiency. Several team members suggest switching to this new technology. The project baseline was approved six months ago, and 30% of the work is complete. The sponsor is known to be cost-conscious and values innovation. What is the best course of action?

August 11, 2026

20
Business EnvironmentPredictiveMedium

A project manager is leading a predictive software implementation project for a regional bank. During the planning phase, the legal department notifies the project manager that a new financial regulation will take effect in six months, requiring additional data encryption features. The regulation was not included in the original business case or project charter. The project is currently on schedule with detailed requirements already baselined. What should the project manager do first?

August 11, 2026

21
Business EnvironmentPredictiveEasy

A project manager is leading a construction project to build a new manufacturing facility. During the planning phase, the sponsor asks how the project aligns with the organization's strategic objectives. The project manager reviews the project charter and identifies that the new facility will increase production capacity by 40%, directly supporting the company's five-year growth plan to expand market share. The sponsor requests a document that formally links the project to these strategic objectives. What document should the project manager provide?

August 11, 2026

22
Business EnvironmentPredictiveEasy

A pharmaceutical company is managing a predictive project to develop a new drug delivery system. Six months into the 18-month project, a competitor announces they will release a similar product in 12 months. The project manager realizes this external change could significantly impact the project's market advantage and business value. The project is currently on schedule and within budget. What should the project manager do first?

August 11, 2026

23
Business EnvironmentPredictiveEasy

A project manager is assigned to lead an infrastructure upgrade project for a government agency. During initial planning, the project manager learns that new regulatory requirements for data security will take effect in three months, midway through the planned project timeline. These regulations will mandate additional security controls that were not included in the original project scope. The project is using a predictive approach with a fixed budget. What is the most appropriate action?

August 11, 2026

24
Business EnvironmentPredictiveEasy

A manufacturing company is implementing an ERP system using a predictive project approach. The project manager notices that the IT department, which will maintain the system after go-live, has not been actively involved in the project. The IT manager mentions they were not aware of specific technical requirements being finalized. The project is 60% complete, and user acceptance testing is scheduled to begin in six weeks. What should the project manager have done differently during project planning?

August 11, 2026

25
Business EnvironmentPredictiveEasy

A project manager is leading a software development project for a retail company using a predictive waterfall methodology. Three months into the project, the company merges with another organization, and the new executive team announces a shift in corporate strategy toward e-commerce rather than brick-and-mortar operations. The current project focuses on in-store point-of-sale systems. The project manager's system is still technically needed but may have reduced priority. What is the best course of action?

August 11, 2026