Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
320 questions found · page 1 of 13
A project manager is leading a government defense project using a predictive methodology with strict earned value management requirements. At the 60% completion milestone review, the project shows CPI of 0.92 and SPI of 0.88. During the review, a government auditor identifies that several procurement processes did not fully comply with new federal acquisition regulations that took effect 4 months ago, though the contracts themselves are valid. The non-compliance issues are administrative rather than substantive, but could trigger a formal audit and potential penalties. The project sponsor suggests quietly correcting the processes going forward without reporting the past issues to avoid audit delays. The project manager knows that government contracts require disclosure of compliance issues. What is the MOST appropriate course of action?
November 18, 2026
A project manager is overseeing a large construction project using a predictive approach when the organization announces a major merger with a competitor. The merger brings significant organizational changes including new executives, revised strategic priorities, and potential consolidation of project portfolios. The project is 55% complete and on track to deliver within baseline constraints. However, three weeks after the merger announcement, the project manager learns informally that a similar project exists in the acquired company and both projects may be evaluated for continuation. The formal portfolio review is scheduled for 8 weeks away. The project team is concerned about job security, and two key resources have started interviewing elsewhere. What should the project manager do?
November 18, 2026
A pharmaceutical company is executing a predictive project to build a new manufacturing facility. The project is 40% complete when a competitor announces a breakthrough technology that could make the planned facility's production method obsolete within 3-5 years instead of the projected 15-year lifecycle. The project has already spent $45M of a $120M budget. Market analysts predict the competitive landscape will shift significantly, but there is uncertainty about regulatory approval timelines for the new technology. The project sponsor wants to continue as planned, citing sunk costs and the need for near-term production capacity. Senior executives are divided. What is the MOST appropriate action for the project manager?
November 18, 2026
A project manager is leading a multinational software implementation project using a predictive waterfall methodology across five countries. During the design phase, the project team discovers that the technology architecture approved in the planning phase conflicts with data sovereignty laws recently clarified by regulators in two of the target countries, representing 35% of the user base. The legal department confirms the architecture cannot be used as designed. The project is already 3 months into an 18-month timeline, and the architecture was a key dependency for vendor selection. The governance board meets quarterly, with the next meeting in 6 weeks. How should the project manager proceed?
November 18, 2026
A large government infrastructure project is in its execution phase when new environmental regulations are enacted that significantly impact the project's deliverables. The project uses a predictive approach with detailed baseline requirements established 18 months ago. The regulatory change requires substantial modifications to the technical specifications, potentially adding 8 months and $4.2M to the project. Senior management pressures the project manager to absorb these changes within the existing schedule and budget constraints to avoid negative stakeholder perception. The contract with the primary vendor has a fixed-price component for 60% of the work. What should the project manager do FIRST to address this situation?
November 18, 2026
You are managing an enterprise software implementation project using a predictive approach. During the executing phase, you notice that your business analyst, who is critical to requirements validation, frequently contradicts decisions made in meetings and repeatedly reopens settled issues. This is causing frustration among stakeholders and the technical team. The business analyst is technically competent and well-intentioned but seems to distrust the process. What is the best approach to address this situation?
November 14, 2026
You are managing a defense project with a geographically distributed team across three locations in different time zones. Team members were selected by functional managers and assigned to your project. During the first two months, you notice that collaboration is minimal, decisions are delayed waiting for email responses, and different locations are developing conflicting approaches to common problems. What should you prioritize to improve team effectiveness?
November 14, 2026
Your pharmaceutical project has a detailed resource histogram showing peak resource demand in months 5-7, requiring 15 specialized scientists. During month 3, the functional manager informs you that due to another urgent project, only 10 scientists will be available during your peak period. The project schedule was approved by the steering committee and cannot slip. What should you do first?
November 14, 2026
You are leading a construction project that is currently in the execution phase. One of your senior engineers, who has been with the project since initiation, has been consistently missing important details in technical reviews, causing rework. You've noticed this team member appears disengaged during meetings and has mentioned personal stress. Other team members are beginning to complain about the quality issues. What is the most appropriate first action?
November 14, 2026
You are managing a government infrastructure project using a predictive approach with a fixed timeline of 18 months. During the planning phase, you identify that your team lacks expertise in specialized soil engineering required for Phase 2, which begins in month 7. The procurement process for external resources takes 3-4 months in your organization. Your sponsor suggests waiting until Phase 1 completes before addressing this gap. What should you do?
November 14, 2026
You are managing an enterprise software implementation project following a waterfall approach. The project has a core team of eight people, including business analysts, developers, and testers. You've noticed that during team meetings, three team members consistently dominate discussions while the other five rarely contribute ideas or feedback. The quieter team members have valuable expertise that could benefit the project. What should you do to improve team participation?
November 14, 2026
You are managing a manufacturing project with a detailed project schedule and assigned resources. The project sponsor has requested that you prepare a resource management plan. You need to document how you will acquire, develop, and manage the project team throughout the project lifecycle. Which of the following should be included in this plan?
November 14, 2026
You are managing a product development project using a predictive methodology. During a weekly team meeting, one of your team members publicly criticizes another team member's work quality on a recent deliverable, stating it was 'sloppy and unprofessional.' The criticized team member becomes visibly upset and defensive. The tension in the room is affecting the rest of the meeting. How should you respond to this situation?
November 14, 2026
You are leading a construction project following a predictive approach. A new civil engineer has joined your team, replacing someone who left the company. The new engineer has strong technical credentials but has never worked on this type of infrastructure project before. Your project is currently in the execution phase, and the work breakdown structure shows that foundation work will begin in three weeks. What is the most appropriate action to help integrate this team member?
November 14, 2026
You are managing a predictive software development project with a team of 12 developers. During the planning phase, you notice that two senior developers have conflicting ideas about the technical architecture approach. The disagreement is causing delays in finalizing the technical design document, which is needed before coding can begin. The project schedule shows that the design phase should be completed in two weeks. What should you do first?
November 14, 2026
A project manager is executing a government contract project using a predictive approach. The project has strict compliance requirements and formal change control processes. A new technology solution becomes available that could reduce project costs by 15% and improve the final product's performance. However, implementing this technology would require significant design changes and extend the schedule by two months. The contract includes performance incentives for early completion. What should the project manager evaluate first when considering this opportunity?
November 11, 2026
A project manager is leading a manufacturing facility expansion project. Six months into the 18-month project, the company announces a merger with a competitor. The merger brings uncertainty about future facility requirements, as the combined organization may need different capacity than originally planned. The project baseline called for doubling production capacity, but the merger may change this requirement significantly. Senior leadership has not yet decided whether to continue, pause, or cancel the project. What should the project manager do?
November 11, 2026
A project manager is leading an infrastructure upgrade project for a financial services company. During execution, a major economic downturn occurs, and the organization announces a 20% budget cut across all projects. The CFO has requested all project managers to identify cost reduction options. The project is currently on schedule and within budget, with 30% of the work completed. Several vendors have already been contracted for upcoming phases. What should the project manager prioritize when developing cost reduction recommendations?
November 11, 2026
A pharmaceutical project manager is overseeing a new drug development project using a predictive approach. During the planning phase, the project team identifies that a key competitor has announced a similar product launch scheduled six months before their planned release date. The executive leadership is pressuring the project manager to accelerate the timeline to maintain competitive advantage. However, the project includes mandatory regulatory approval phases that cannot be compressed. What is the best course of action?
November 11, 2026
A project manager is leading a predictive construction project when new environmental regulations are announced that will affect the project's compliance requirements. The project is 40% complete, and the regulations will take effect in three months, midway through the project timeline. The regulatory changes will require additional environmental impact assessments and potentially design modifications. Stakeholders are concerned about project costs and schedule. What should the project manager do first?
November 11, 2026
You are managing a software implementation project for a financial services client using a waterfall methodology. During the design phase, the client's compliance officer requests changes to the security architecture to address new regulatory requirements that were published last month. Implementing these changes will require rework of completed design documents and delay the project by four weeks. The compliance officer emphasizes that non-compliance could result in significant fines. What is the best approach to handle this situation?
November 11, 2026
During the planning phase of a pharmaceutical research project, you are developing the project schedule. Several senior researchers insist that certain experimental activities cannot have their durations estimated accurately because the outcomes are uncertain. However, your management wants a detailed schedule with specific milestones for board reporting. The contract includes penalty clauses for late delivery. How should you address duration estimating for these uncertain activities?
November 11, 2026
You are managing a manufacturing equipment installation project following a predictive lifecycle. During quality inspections, your quality team identifies that several delivered components do not meet the specifications detailed in the technical requirements document, though they could still function adequately. The supplier claims these components meet industry standards and modifying them would delay delivery by six weeks and increase costs by 15%. The project is currently on schedule and within budget. What should you do?
November 11, 2026
Your construction project is halfway through execution when you discover that actual costs are significantly higher than planned. The Cost Performance Index (CPI) is 0.78 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks for your assessment of the situation and whether the project can be completed within the approved budget. You have $2 million remaining in the budget and estimate $3.2 million of work left to complete. What is the most appropriate course of action?
November 11, 2026
You are managing a government infrastructure project using a predictive approach. During the executing phase, a key supplier notifies you that they cannot deliver critical materials by the scheduled date due to manufacturing delays, which will impact the critical path by three weeks. The project has a fixed deadline tied to regulatory approval timelines. Your sponsor is concerned about potential penalties. What should you do first?
November 11, 2026
