Practice Questions
PMP Practice Questions
Scenario-based questions aligned with the 2026 PMP Exam Content Outline. All questions reviewed by a certified PMP before publishing.
75 questions found · page 1 of 3
You are managing a product development project using a stage-gate approach. The project is approaching the gate review for Phase 2 completion. During quality inspections, you discover that three of the fifteen deliverables have minor defects that do not prevent functionality but fall slightly below the quality standards documented in the quality management plan. Correcting these defects would take two weeks and consume the remaining schedule buffer. The gate review is scheduled for next week, and senior management is eager to proceed to Phase 3. What should you do?
July 10, 2026
You are managing an infrastructure project with a detailed WBS and network diagram. A key stakeholder requests the addition of a new feature that was not included in the original scope baseline. The change would provide significant value to end users and has strong executive support. After analysis, you determine the change would add three weeks to the schedule and increase costs by 8%. The change control board (CCB) has approved the change request. What should you do next?
July 10, 2026
Your manufacturing project has a Cost Performance Index (CPI) of 0.85 and a Schedule Performance Index (SPI) of 1.10. The project is 60% complete with six months remaining until the planned completion date. During the monthly steering committee meeting, the CFO expresses concern about the budget overrun and asks whether the project can be completed within the approved budget. What should you present to the steering committee?
July 10, 2026
You are leading a software development project using a waterfall methodology. During the testing phase, the QA team discovers that 15% of the delivered functionality does not meet the acceptance criteria defined in the requirements document. The development team claims the requirements were ambiguous and their interpretation was reasonable. The testing phase is scheduled to end in one week, and any rework will delay the go-live date. What is the most appropriate action?
July 10, 2026
You are managing a construction project using a predictive approach. During the execution phase, a supplier informs you that a critical material will be delayed by three weeks due to manufacturing issues. This delay will impact the critical path and push the project completion date beyond the contractual deadline. You have already exhausted schedule reserves on previous delays. The project sponsor is highly concerned about contractual penalties. What should you do first?
July 10, 2026
You are managing a complex infrastructure project using earned value management and a predictive approach. Your project has a CPI of 0.92 and SPI of 0.88, indicating both cost and schedule challenges. During a difficult steering committee meeting, your sponsor publicly criticizes your leadership and questions your competence in front of other executives and your project team members who were presenting. The sponsor demands immediate corrective actions and threatens to replace you if performance doesn't improve by next month. After the meeting, your team members express concern about the public criticism, and you sense their confidence in the project's success is wavering. What should be your FIRST priority in responding to this situation?
July 10, 2026
You are managing a multinational aerospace engineering project with team members across five countries and three time zones, following a stage-gate predictive methodology. During the design phase, you discover that your lead engineers in Germany and Japan have been making conflicting technical decisions in their respective subsystems, each believing they had authority over the integration approach. This has resulted in incompatible design specifications that were just revealed during a scheduled integration review, three weeks before the gate review. Both engineers are highly respected technical authorities who report to different functional managers in a strong matrix organization. The functional managers are now involved and supporting their respective engineers' approaches. How should you address this situation?
July 10, 2026
You are managing a pharmaceutical manufacturing facility construction project following a waterfall approach. During the executing phase, you notice that your quality manager and construction manager have fundamentally different interpretations of the acceptance criteria in the approved requirements specification. The quality manager insists on FDA pharmaceutical-grade standards for all areas, while the construction manager argues that only clean room areas require this level, with administrative areas following commercial building standards. Both cite different sections of the 300-page requirements document. This disagreement is causing daily conflicts, delaying inspections, and creating team tension. How should you resolve this conflict?
July 10, 2026
You are leading a government IT system integration project using a predictive lifecycle with a dedicated team of 25 members. Six months into the 24-month project, organizational metrics show your team's velocity is 15% below the planned baseline, though quality metrics remain acceptable. During a retrospective session, team members confidentially share that the project's strict command-and-control governance structure, mandatory daily status emails, and your directive leadership style are demotivating them. Several high performers hint they are exploring other opportunities. However, the government client has explicitly required this governance approach due to previous project failures, and your sponsor strongly supports maintaining tight controls. What is the BEST course of action?
July 10, 2026
You are managing a critical defense infrastructure project with a fixed 18-month timeline and strict requirements documentation. Three months into execution, your technical lead, who designed the entire system architecture, submits a resignation effective in two weeks to join a competitor. This person holds critical knowledge not fully documented, and the remaining team members have varying levels of expertise. Senior management is extremely concerned about project continuity and wants to prevent knowledge loss. What should be your FIRST action as project manager?
July 10, 2026
You are managing a complex systems integration project following a predictive lifecycle. Three months before a major milestone delivery, your technical lead identifies that integrating two vendor systems will require an interface component that was not in the original design. Without this component, the systems cannot communicate, and the milestone deliverable cannot function. Analysis shows: developing the interface will cost $185K and take 8 weeks; the milestone is on the critical path; contingency reserve has $120K remaining; and both vendors claim the interface requirement was implied in the SOW but not explicitly stated. Your legal team is investigating liability. What should you prioritize as project manager?
July 8, 2026
Your construction project is in month 18 of a 30-month schedule. A new environmental regulation has been enacted that requires additional soil remediation procedures for your project site. The regulation applies retroactively to work already completed. Your legal team estimates compliance will add $1.2M in costs and 3 months to the schedule. You have management reserve of $800K and schedule reserve of 6 weeks. The contract includes a force majeure clause and regulatory change provisions. Your CFO wants to minimize financial impact, your customer is concerned about schedule, and your legal counsel advises documenting everything for potential claims. What is your best course of action as the project manager?
July 8, 2026
You are managing a government defense project with strict predictive controls and a fixed-price contract. During the testing phase, quality inspections reveal that 18% of manufactured units fail to meet specification tolerances defined in the quality management plan. Investigation shows the root cause is a calibration drift in manufacturing equipment that began gradually six weeks ago. The cost of rework is $340,000, and recalibrating will halt production for one week, impacting the critical path. Your quality manager wants to adjust acceptance criteria to pass more units, your operations manager wants to continue production and rework later, and your sponsor wants to understand the control implications. What should you do first?
July 8, 2026
Your pharmaceutical project is developing a new drug delivery system using a predictive approach. During the design phase, a critical supplier notifies you that a key component's lead time has increased from 8 weeks to 20 weeks due to raw material shortages. This component is needed for three activities on the critical path and two on a near-critical path (total float of 5 days). The project is currently on schedule, and regulatory submission deadlines are contractually fixed. Your team proposes four risk response strategies. Which response best addresses this threat while maintaining predictive project controls?
July 8, 2026
You are managing a complex infrastructure project with a 24-month timeline and a $15M budget. During month 14, earned value analysis shows: PV = $8.5M, EV = $7.2M, AC = $8.1M. The project has experienced significant scope changes, and three critical path activities are behind schedule. Your sponsor asks for a realistic forecast of final project cost and wants to understand if the current cost performance will continue. Considering the CPI trend has been declining over the past four months from 0.92 to 0.89, what is the most appropriate estimate at completion (EAC) to present?
July 8, 2026
You are managing a predictive project to implement a new financial reporting system. Midway through the project, your lead business analyst, who has been with the company for 15 years and knows the legacy systems intimately, announces she will retire in six weeks. Her knowledge is crucial for the remaining requirements validation and user acceptance testing phases scheduled over the next three months. She is willing to help with transition activities before leaving. What is your best course of action?
July 8, 2026
You are leading a predictive infrastructure project with team members from three different departments. During the third monthly project review meeting, you notice that members from the operations department consistently remain silent when asked for input, even on topics directly affecting their work. Later, one operations team member privately tells you they feel their opinions don't matter because engineering always dominates the discussions. The project requires integrated input from all departments to succeed. How should you address this situation?
July 8, 2026
Your predictive manufacturing project is entering the execution phase with a baseline schedule approved by all stakeholders. You discover that a key subject matter expert, who was promised to your project at 50% allocation, is now only available 20% due to competing organizational priorities. This resource was critical for your planned knowledge transfer sessions with the implementation team. The functional manager apologizes but says they cannot change the allocation. What should you do?
July 8, 2026
You are managing a construction project using a predictive approach with a detailed WBS and Gantt chart. Three months into the six-month project, you notice that one of your team leads has been consistently missing status meeting deadlines and providing incomplete progress reports. However, their team's deliverables are being completed on time and meeting quality standards. Other team leads have started complaining about the inconsistent reporting. What is the most appropriate action?
July 8, 2026
You are managing a predictive software development project with a team of 12 members. During the planning phase, you notice that two senior developers, who must work closely on the database architecture, have a history of conflict from a previous project. The project schedule is tight, and their collaboration is critical for meeting the milestone dates. Team morale appears positive otherwise, but you're concerned this unresolved tension could impact performance. What should you do first?
July 8, 2026
You are managing a product development project using a predictive approach. The project management plan has been approved and execution has begun. During a team meeting, you realize that several team members are unclear about their specific responsibilities and who has decision-making authority for various project activities. This confusion is beginning to cause delays. What document should you reference or update to clarify these roles and responsibilities?
July 2, 2026
You are leading a predictive infrastructure project that is currently in the executing phase. A stakeholder who was not involved in initial planning requests a significant change to the project scope that would add new deliverables. The stakeholder insists the change is critical and wants it implemented immediately. What is the most appropriate action to take?
July 2, 2026
You are managing a manufacturing project to develop a new product line. During the execution phase, one of your team members discovers that a delivered component does not meet the specifications documented in the project requirements. The supplier claims the component meets industry standards, but it clearly does not match what was agreed upon in the procurement contract. What should be your first step?
July 2, 2026
You are planning a software implementation project for a financial services company. The project sponsor has approved a budget of $500,000. During cost planning, you need to establish a performance measurement baseline that will be used to monitor and control project costs throughout execution. The baseline should integrate scope, schedule, and cost to enable earned value management. What should you create?
July 2, 2026
You are managing a construction project to build a new office building. During the planning phase, you need to determine the total project duration by analyzing the sequence of activities and their dependencies. You have identified all activities, estimated their durations, and mapped out their logical relationships. What technique should you use to calculate the longest path through the project and identify the minimum project duration?
July 2, 2026
