PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 4.2

PMP Practice Question: Process — Predictive, Medium

You are leading a software development project using a waterfall methodology. During the testing phase, the QA team discovers that 15% of the delivered functionality does not meet the acceptance criteria defined in the requirements document. The development team claims the requirements were ambiguous and their interpretation was reasonable. The testing phase is scheduled to end in one week, and any rework will delay the go-live date. What is the most appropriate action?

← All questions

Study this topic