You are managing an infrastructure project with a detailed WBS and network diagram. A key stakeholder requests the addition of a new feature that was not included in the original scope baseline. The change would provide significant value to end users and has strong executive support. After analysis, you determine the change would add three weeks to the schedule and increase costs by 8%. The change control board (CCB) has approved the change request. What should you do next?