ProcessPredictiveHardECO: Process Task 7.2 - Plan and manage quality of products/deliverables

You are managing a government defense project with strict predictive controls and a fixed-price contract. During the testing phase, quality inspections reveal that 18% of manufactured units fail to meet specification tolerances defined in the quality management plan. Investigation shows the root cause is a calibration drift in manufacturing equipment that began gradually six weeks ago. The cost of rework is $340,000, and recalibrating will halt production for one week, impacting the critical path. Your quality manager wants to adjust acceptance criteria to pass more units, your operations manager wants to continue production and rework later, and your sponsor wants to understand the control implications. What should you do first?

← All questions
📖

Study this topic

WBS Work Breakdown Structure: Proven Best Practices

Master the essential techniques for creating effective Work Breakdown Structures that drive project success and align wi