ProcessPredictiveHardECO: Process Task 5.2 - Plan and manage project compliance

Your pharmaceutical project is developing a new drug delivery system using a predictive approach. During the design phase, a critical supplier notifies you that a key component's lead time has increased from 8 weeks to 20 weeks due to raw material shortages. This component is needed for three activities on the critical path and two on a near-critical path (total float of 5 days). The project is currently on schedule, and regulatory submission deadlines are contractually fixed. Your team proposes four risk response strategies. Which response best addresses this threat while maintaining predictive project controls?