ProcessPredictiveMediumECO: Process Task 2.4

Your manufacturing project has a Cost Performance Index (CPI) of 0.85 and a Schedule Performance Index (SPI) of 1.10. The project is 60% complete with six months remaining until the planned completion date. During the monthly steering committee meeting, the CFO expresses concern about the budget overrun and asks whether the project can be completed within the approved budget. What should you present to the steering committee?