PMP Guide — Empowering Project Managers
ProcessPredictiveEasyECO: Process Task 2.1

PMP Practice Question: Process — Predictive, Easy

You are managing a construction project to build a new office building. During the planning phase, you need to determine the total project duration by analyzing the sequence of activities and their dependencies. You have identified all activities, estimated their durations, and mapped out their logical relationships. What technique should you use to calculate the longest path through the project and identify the minimum project duration?

← All questions

Study this topic