PMP Practice Question: Process — Predictive, Medium

You are managing a product development project using a stage-gate approach. The project is approaching the gate review for Phase 2 completion. During quality inspections, you discover that three of the fifteen deliverables have minor defects that do not prevent functionality but fall slightly below the quality standards documented in the quality management plan. Correcting these defects would take two weeks and consume the remaining schedule buffer. The gate review is scheduled for next week, and senior management is eager to proceed to Phase 3. What should you do?