PMP Guide — Empowering Project Managers
ProcessPredictiveMediumECO: Process Task 3.2

PMP Practice Question: Process — Predictive, Medium

You are managing a construction project using a predictive approach. During the execution phase, a supplier informs you that a critical material will be delayed by three weeks due to manufacturing issues. This delay will impact the critical path and push the project completion date beyond the contractual deadline. You have already exhausted schedule reserves on previous delays. The project sponsor is highly concerned about contractual penalties. What should you do first?

← All questions

Study this topic

PMP Practice Question — Process · Medium | PMP Guide