PMP Practice Question: Process — Predictive, Medium
You are managing a construction project using a predictive approach. During the execution phase, a supplier informs you that a critical material will be delayed by three weeks due to manufacturing issues. This delay will impact the critical path and push the project completion date beyond the contractual deadline. You have already exhausted schedule reserves on previous delays. The project sponsor is highly concerned about contractual penalties. What should you do first?
Study this topic
- 📖Critical Path Method: Mastering CPM for Project Success
Learn how to master the Critical Path Method for the PMP exam and real-world project management. Understand float calculation, network diagrams, and schedule optimization techniques.
- 📖Dependencies and Sequencing in Project Scheduling
Master the logic of task dependencies and sequencing to build realistic, defensible project schedules that account for constraints and optimize resource flow.
- 🗂️Flashcards: Schedule, Estimating & Financial Formulas
14 cards · quick recall practice
More Process Questions
View all →You are managing a construction project with a fixed budget of $2.5 million and a 14-month timeline. During month 6, you conduct an earned value analysis and discover that the Cost Performance Index (CPI) is 0.85 and the Schedule Performance Index (SPI) is 0.92. The project sponsor asks you to forecast the final project cost and determine what actions are needed. Using the current performance trends, what is the most appropriate estimate at completion (EAC) if you believe current variances are atypical and future work will be performed at the planned rate?
You are leading a software development project using a predictive approach. The project sponsor has approved the project charter, and you are now ready to begin detailed planning. Your next step is to gather requirements from stakeholders to understand what the software must accomplish. Which process group are you currently working in?
You are managing a bridge construction project and have just completed developing the Work Breakdown Structure (WBS) with your team. Each work package has been defined and assigned a unique identifier. A team member asks what the lowest level of the WBS represents. How should you respond?