ProcessHybridHardECO: Process Task 2.5

You are leading a transformation project using a hybrid approach where infrastructure deployment follows a predictive model and application features are developed iteratively. The project baseline includes a fixed budget of $2M and a 12-month timeline. After 6 months and $1.1M spent, earned value analysis shows CPI of 0.91 and SPI of 0.88. Meanwhile, the adaptive track has delivered 45% of planned story points with high stakeholder satisfaction. The sponsor questions whether the project is failing and considers cancellation. How should you respond?